Glossary

Project Controls & Schedule Analysis Glossary

Plain-English definitions for the terms that come up in construction scheduling, project controls, and schedule delay analysis. Vendor-neutral: where a term maps to a live Pathizer capability, it is noted honestly.

Line drawing of a hand underlining a line in a notebook, with rolled drawings and a tablet beside it

Contracts, changes and payment

Beneficial occupancy
The owner using a building, or part of one, for its intended purpose while minor work that does not affect that use goes on. For example, a school opens its classroom wing while the gym is finished. Under FAR 52.236-11, early use is not acceptance, and time or price is adjusted if it delays the contractor.
Change order
A written change to the contract's work, price or time. On federal jobs, FAR defines it as an order signed by the contracting officer, which can direct a change without the contractor's consent.
Constructive change
A change the owner never wrote up as one. Direction, interpretation or inaction makes the contractor do more or different work than the contract requires. For example, an inspector insists on a finish the specifications do not call for.
Contract completion date
The date the contract sets for finishing the work, or a defined part of it. It is a calendar date or a number of days after notice to proceed.
Differing site conditions
Physical conditions at the site that are not what the contract showed. The federal clause, FAR 52.236-2, names two kinds. The first is hidden or subsurface conditions that differ materially from the contract documents. The second is unusual unknown conditions that differ from what that kind of work normally runs into. Rock where the borings showed clay is the classic case. The clause asks for prompt written notice before the conditions are disturbed.
Extended general conditions
Time-related site costs (for example supervision, the field office and temporary facilities) that run longer because the job did. They are usually priced at a daily rate (total general conditions divided by the days of performance) or from actual costs during the delay period. The contract, and a compensable delay, decide if they are recoverable.
Final acceptance
The owner's formal acceptance of the finished work after the last inspection, which releases final payment. Under FAR 52.232-5, federal final payment follows completion and acceptance of all work and a release of claims. So any claim the contractor means to keep has to be listed as an exception in that release.
Liquidated damages
A daily amount, fixed in the contract, that the contractor owes for each day the work finishes late. Under FAR 52.211-12 it applies for each calendar day of delay until the work is completed or accepted. With the rate known in advance, every forecast day late has a price.
Notice to proceed (NTP)
The owner's written go-ahead to start work. Contract time usually counts from it. A limited NTP releases only part of the work, for example design or early procurement.
Pay application
The contractor's periodic request for payment, billed line by line against the schedule of values. On a cost-loaded schedule, end the pay period on the data date so the update and the bill agree.
Retainage
Money held back from each progress payment until the work is finished and accepted. Under FAR 52.232-5 the government may hold up to 10 percent while progress is unsatisfactory. At substantial completion it keeps only what it needs for protection.
Schedule of Values (SOV)
The contract price split into line items of work, which progress is billed against each month. An SOV that lines up with the schedule's activities is what lets cost be tied to the schedule.
Substantial completion
The point where the work, or a defined part of it, is finished enough for the owner to use it for its intended purpose. Only punch list work is left. The architect or engineer usually certifies it, and the contract says what it triggers. On federal jobs, for example, part of the retainage can be released at substantial completion.
Suspension of work
An order to stop, delay or interrupt all or part of the work. Under FAR 52.242-14 the contractor can recover the added cost, without profit. This applies only when the contracting officer's act or failure to act holds up the work for an unreasonable period. Costs incurred more than 20 days before written notice are not recoverable, except under a written suspension order.

Cost, resources and production

Cash flow curve
Money in and money out plotted over time. For a contractor it shows the gap between paying crews and suppliers and getting paid.
Cost-loaded schedule
A schedule whose activities carry dollars, so one file shows when work happens and what it is worth. It is the base for earned value and for billing progress from the update. In Pathizer, cost loading is on the roadmap, not available today.
Cost Performance Index (CPI)
Earned value divided by actual cost. A CPI of 0.90 means each dollar spent is earning 90 cents of budgeted work.
Earned value
A way to measure progress in budget terms. Each piece of work is worth its budget, and as it gets done it earns that value. On a $2 million mechanical package that is 40 percent complete, earned value is $800,000, whatever has been spent. Comparing earned value with planned value shows schedule performance, and comparing it with actual cost shows cost performance.
Labor curve
A chart of crew size over time, by week and trade, drawn from a resource-loaded schedule. A spike to 60 electricians on a job that has never had more than 25 is a plan to question.
Productivity
Output for the hours put in, for example linear feet of pipe per labor hour. When it drops, the work takes more hours and often more days.
Resource leveling
Adjusting the schedule so demand for a crew or a piece of equipment stays within what is available. When a scheduling tool levels resources, it moves lower-priority activities until the resource fits, which can push dates out and use up float. A leveling log, where the tool writes one, lists what was delayed, so read it before trusting the new dates.
Resource loading
Assigning labor, equipment or cost to activities so the schedule carries quantities, money and dates. It shows if the crew the plan needs exists. Four ironworkers on each of three overlapping deck activities is twelve, on a site that may have eight.
S-curve
A cumulative plot of cost, labor hours or progress against time, flat at the start and end and steep in the middle. Plotting planned and actual curves together shows if the work is ahead or behind in dollars or hours. Risk analysis uses the same name for the cumulative curve of possible finish dates.
Schedule Performance Index (SPI)
Earned value divided by planned value. An SPI of 0.85 means 85 percent of the work planned by now, in dollars, is done. Because it counts dollars of work, it can read 1.0 while critical activities fall behind and noncritical work runs ahead.
Unit rate
The cost or labor hours for one unit of work, for example dollars per cubic yard of concrete or hours per ton of steel. Unit rates turn quantities into durations and costs.
Work Breakdown Structure (WBS)
The project scope broken down level by level (for example building, floor and trade), with every schedule activity filed under one package.

Critical path, float and recovery

Crashing
Shortening an activity by spending more on it: a second shift, overtime, more crews or more equipment. It helps the finish date only when the activity is on the critical path.
Critical activities setting
The scheduling option that decides which activities get flagged critical. It can use a total float threshold (for example zero or less) or the longest path. Either method can flag activities that do not drive the finish, for example open ends or constrained activities. Check the option before reading the critical flag.
Critical activity
An activity on the critical path. A day lost on it is a day lost on the finish unless the time is made up later.
Critical path
The chain of dependent activities that sets the project's finish date. On a hospital fit-out it might run through generator delivery, switchgear energization and life safety testing.
Critical Path Method (CPM)
The scheduling method behind a logic-driven construction schedule. It uses activities with durations and logic ties, and a forward pass for early dates. A backward pass gives late dates, and float is the difference between them.
Early and late dates
Early dates are the first the logic allows, from the forward pass. Late dates are the last the work can happen without moving the finish, from the backward pass. The gap between them is total float.
Fast-tracking
Overlapping work that would normally run in sequence, for example starting foundations before the upper floors are fully designed. It saves time and adds the risk of rework.
Float consumption
Float used up between updates. A ductwork activity that had 30 days of float in March and 8 in May has consumed 22 days. That is true even if nobody called it a delay. Track it by path, because a path losing float every month can become critical.
Float (total / free)
Room to slip. Total float is how long an activity can slip without moving the project finish. Free float is how long it can slip without delaying the early start of any successor.
Forward pass and backward pass
The two CPM calculations. The forward pass runs from the data date to the finish to get early dates. The backward pass runs from the finish back to get late dates. Late minus early is total float.
Longest path
The chain of activities that actually drives the completion date. Activities flagged critical by a float threshold are not always on it, which is why delay is measured against the longest path.
Multiple float paths
A scheduling option that sorts the activities leading to a chosen end activity into numbered paths. Float Path 1 is the critical one, then 2, 3 and so on in order of float. Calculated by free float, path 1 matches the longest path. It shows a superintendent what is second and third in line behind the critical path. Pathizer's Network Diagram shows these float paths activity by activity.
Near-critical
Activities whose total float is close to the critical path's, so a small slip makes them critical. There is no universal threshold. GAO leaves it to each program and gives 5 days or less of total float as an example, and some scheduling trainers use 10 days. Watching the near-critical paths from update to update shows which one is gaining on the critical path.
Negative float
Total float below zero: the forecast is later than a date the schedule has to meet, usually a constrained contract milestone. If the End Project milestone is constrained to the contract completion date and the forecast runs 12 days past it, that path shows minus 12. DCMA check 7 expects any negative float to come with an explanation and a mitigation plan.
Recovery schedule
A schedule showing how lost time will be made up through more crews, longer hours or extra workdays. On federal work, FAR 52.236-15 lets the contracting officer require supplementary schedules showing how the planned rate of progress will be regained. USACE specifications do not allow the forecast to be improved by tightening logic, durations or calendars without a stated basis. Added crews have to show up on site and in the daily reports.
Schedule compression
Any way of shortening the remaining critical path: re-sequencing, overlapping work (fast-tracking) or adding resources (crashing).
Schedule risk analysis
A Monte Carlo simulation run on a CPM schedule, using a range of durations for each activity plus the identified risks. It shows how confident the team can be in a finish date. GAO's schedule guide uses it to size schedule contingency for a chosen confidence level and to rank the risks.

DCMA 14-point checks

Baseline Execution Index (BEI) (DCMA check 14)
Activities completed, divided by the activities the baseline said would be complete by the data date. A BEI of 1.0 means work is finishing at the planned rate, and below 0.95 gets flagged. If 50 activities were due and 40 are done, BEI is 0.80. It counts activities without weighing their importance, so read it next to the critical path.
Critical Path Length Index (CPLI) (DCMA check 13)
Critical path length plus total float, divided by critical path length. It shows how efficiently the remaining critical path has to run to finish on time. A CPLI of 1.0 is on track and below 0.95 gets flagged. With 200 working days of remaining critical path and minus 10 days of float, CPLI is 190 divided by 200, or 0.95.
Critical path test (DCMA check 12)
Add a large delay to an incomplete critical activity near the start of the schedule, then recalculate. If the critical path is continuous, the project finish moves by the same amount. If it moves less or not at all, something breaks the chain, for example a hard constraint or an open end. Some guides use a 600-day test delay. The size matters less than seeing the finish move day for day.
DCMA 14-Point Assessment
Fourteen schedule health checks from the Defense Contract Management Agency's EVMS Program Analysis Pamphlet (DCMA-EA PAM 200.1). They cover logic, leads, lags, relationship types, hard constraints, high float and negative float. They also cover high duration, invalid dates, resources, missed tasks, the critical path test, CPLI and BEI. Many scheduling tools run versions of them in their own schedule check reports. A missed threshold is a reason to look closer. Health Score calculates the fourteen checks from the schedule data, so the same inputs give the same result.
Hard constraints (DCMA check 5)
Counts incomplete activities carrying constraints that can override logic. The commonly published threshold is 5 percent. Mandatory Start and Mandatory Finish are the usual hard constraints. Tools differ on which other types they count, so check the settings before comparing scores from two programs. Each hard constraint left in should trace to a contract date.
High duration (DCMA check 8)
Counts incomplete activities with a baseline duration over 44 working days, against a commonly published 5 percent threshold. On a 70-day activity, percent complete is a guess nobody can check.
High float (DCMA check 6)
Counts incomplete activities with more than 44 working days of total float, against a commonly published 5 percent threshold. Large float usually means a missing successor.
Invalid dates (DCMA check 9)
Actual dates after the data date, or forecast dates before it. The threshold is zero. Fix these before running any other check, because they break the meaning of the data date.
Lags (DCMA check 3)
Counts relationships with positive lag, against a commonly published 5 percent threshold. A long lag often stands in for work that should be its own activity. Some scheduling tools' built-in schedule checks also list long lags.
Leads (DCMA check 2)
Counts relationships with negative lag. The threshold is zero. If a crew really can start early, use a start-to-start link with a positive lag, or split the predecessor where the successor can begin.
Missed tasks (DCMA check 11)
Of the activities whose baseline finish falls on or before the data date, the share that finished late or are forecast to. The commonly published threshold is 5 percent.
Missing logic (DCMA check 1)
Counts incomplete activities missing a predecessor, a successor or both, against a commonly published 5 percent threshold. Each one is an open end, and the float around it means little.
Relationship types (DCMA check 4)
The share of relationships that are finish-to-start. The commonly published target is at least 90 percent. Start-to-finish links count against it and should be rare.
Resources (DCMA check 10)
Checks that a resource-loaded schedule is loaded completely, with hours or dollars on every incomplete activity that has duration. A schedule with no resources at all does not fail it.

Delay analysis methods

AACE 29R-03 (MIP)
AACE International Recommended Practice 29R-03, Forensic Schedule Analysis. It names nine Method Implementation Protocols, MIP 3.1 to 3.9, in two groups. Observational methods read the updates as issued. Modeled methods add or subtract delays in a schedule model. Pathizer has a strict run for eight of the nine. MIP 3.5 is a screening of the retained updates, with no run of its own.
As-built schedule
The record of what actually happened: actual start and finish dates for every activity, usually with the logic the work really followed. Retrospective methods start from it.
As-planned vs. as-built
A retrospective method comparing the original plan with what was actually built. It is simple to present, but it skips the updates in between. So it shows less about when and why the critical path changed than methods that follow each update.
Collapsed as-built (but-for)
A retrospective method that removes chosen delays from the as-built schedule to estimate when the job would have finished without them. The answer depends heavily on how the as-built logic was reconstructed.
Contemporaneous update
A schedule update prepared and issued at the time, as opposed to one rebuilt later. Window and half-step analyses rely on these because they show what the parties knew when they made decisions.
Fragnet
A small piece of network, a few activities and their relationships, inserted into a schedule to model a change or delay event between updates.
Half-Step (half-step analysis)
One schedule update split into two steps. First apply only the progress (actual dates and remaining durations) and recalculate, then apply the plan edits (logic, durations, constraints) and recalculate again. The first step shows what the progress did to the finish, and the second shows what the re-planning did. So a slip that new logic hid, or a recovery that only exists on paper, shows up. Pathizer calls the method the Half-Step split (MIP 3.4) and reports each update's Half-Step Changes.
Impacted as-planned
A modeled method that adds delay events to the baseline schedule and recalculates to estimate their effect on completion. Simple to build, but it ignores actual progress and every logic change made after the baseline.
Modeled methods
The AACE 29R-03 family that changes a schedule model and recalculates to measure delay (MIP 3.6 to 3.9). Additive methods insert delay fragnets, using one base for impacted as-planned (MIP 3.6) or several for time impact analysis (MIP 3.7). Subtractive methods take delays out to build a but-for schedule, from a single as-built simulation (MIP 3.8) or several bases (MIP 3.9).
Observational methods
The AACE 29R-03 family that studies schedules as they are, without the analyst inserting or removing delays (MIP 3.1 to 3.5). Static logic methods (MIP 3.1 and 3.2) measure the as-built record against the baseline's logic, the approach commonly called as-planned versus as-built. Dynamic logic methods (MIP 3.3 to 3.5) use the updates, so they follow the critical path as it changed.
Prospective analysis
Delay analysis done while the work is underway, to forecast an event's effect on the current schedule. Time impact analysis is the usual tool.
Retrospective analysis
Delay analysis done after the fact, from the updates and records the project actually produced. Window analysis and collapsed as-built are retrospective methods.
Time Impact Analysis (TIA)
A forward-looking, model-based method. A fragnet for the delay event goes into the schedule in effect when the event happened. The schedule is recalculated, and the change in the completion date is the measured impact. If a 15-day fragnet for a redesigned chiller pad moves the finish 9 days, the other 6 were absorbed by float on that path.
Window analysis
A method that divides the project into time windows, commonly update to update. It measures the delay that happened in each window, following the schedule as it actually evolved.

Delay and entitlement

Acceleration
Finishing earlier than the current schedule allows because the owner requires it. Directed acceleration is ordered outright. In constructive acceleration, a contractor was due a time extension and asked for it, but was refused or answered too late. The owner still expected the original date, and the contractor told the owner it treated that as an order to accelerate.
Concurrent delay
Delays from different parties that affect the driving path in the same period. The contract and governing law decide how concurrency affects time and money. The schedule analysis identifies the overlapping periods.
Delay vs. disruption
Delay moves a date. Disruption lowers productivity or changes how the work is done, sometimes without moving any date. They are measured differently and usually claimed separately.
Excusable and compensable delay
Excusable delay earns the contractor more time, and compensable delay earns time and money. The contract decides which events fall in each class, and the schedule shows how many days each one caused.
Extension of time (EOT), or time extension
Added contract time granted for an excusable delay, usually through a change order or contract modification. Pathizer keeps granted EOT days in a ledger beside the measured delay, so the two can be compared without being merged.
Float ownership
Who gets to use float. Contracts answer it differently. USACE specifications say float belongs to the project and is available to both parties. So no time extension is granted unless a delay uses up the available project float. AACE 29R-03 lists shared ownership of network float as a general principle. The schedule shows how much float a delay consumed; the contract decides whose it was.
Non-excusable delay
Delay the contract leaves with the contractor, so it earns no extra time and can bring liquidated damages. Under FAR 52.249-10, for example, delay is excusable only when it comes from unforeseeable causes beyond the contractor's control and without its fault or negligence. Each contract sets its own list. The schedule shows which activities and events drove the days; the contract decides which category each event falls in.
Notice of delay
Written notice to the owner that an event is delaying, or may delay, the work. FAR 52.249-10 requires written notice of the cause within 10 days of the beginning of any delay. Other contracts set their own deadline and contents. A late notice can put a time extension at risk.
Pacing delay
A deliberate slowdown of work off the critical path, made because another party's delay has already pushed the finish out and opened float. If owner design changes push the critical path out a month, a contractor may slow a parallel steel package and not finish it early. To count as pacing, the decision should be conscious and documented at the time. The schedule shows the float that opened; the contract and governing law decide responsibility.
Weather days
Workdays lost because conditions made the planned work unworkable, measured against the contract's thresholds, for example a minimum rainfall amount. The schedule should already carry normal weather, so an extension usually turns on weather beyond normal that hit activities on the longest path. Rain on a day when only interior finishes were driving rarely qualifies. Pathizer's Weather Days ledger counts days against each contract weather threshold since the start of the project.

Federal and USACE work

Anticipated adverse weather
On USACE contracts, the number of weather workdays expected in each month, written into the contract from historical weather data using the ER 415-1-15 method. Those days belong in the schedule before any claim is made, and USACE prefers a weather calendar for that. A time extension for unusually severe weather needs weather worse than the anticipated level and an impact on activities on the longest path.
Claim (FAR 2.101)
A written demand by either party seeking, as a matter of right, a sum certain, an interpretation of the contract, or other relief. A routine invoice is not a claim, and a contractor claim over $100,000 counts only once certified under FAR 33.207.
FAR 52.236-15, Schedules for Construction Contracts
The federal clause requiring a practicable progress schedule soon after work starts. A contractor that falls behind must add shifts, overtime or equipment at no cost to the government, and the contracting officer can require supplementary schedules. Ignoring it can support a finding of insufficient diligence and default termination.
Request for Equitable Adjustment (REA)
A contractor's request to the contracting officer to adjust contract terms, for example price or time. The cause is a change, a differing site condition or another government action. It usually comes before a formal claim. On DoD contracts, DFARS 252.243-7002 requires certification of an REA above the simplified acquisition threshold and limits it to the costs of performing the change. A time request needs a schedule analysis showing which activities the event delayed.
RMS (Resident Management System)
The USACE system for construction contract administration and quality control. The government works in RMS Government Mode and the contractor in RMS Contractor Mode. RMS handles daily quality control reports, submittals, RFIs, payment requests and schedule data. Current USACE guide specifications say RMS is transitioning to the Construction Management Platform (CMP) during fiscal year 2027, district by district. Check which system your contract names.
SDEF (Standard Data Exchange Format)
The USACE format for exchanging schedule data between a contractor's scheduling software and government systems, defined in ER 1-1-11. UFGS 01 32 01.00 10 also makes the SDEF activity coding structure mandatory, so a contractor's schedule on a Corps job carries SDEF activity codes. Where the contract calls for a weekly progressed schedule upload to the government's construction contract system of record, the file is SDEF or an equivalent.
Three phases of control
The quality control routine in UFGS 01 45 00, used by USACE, NAVFAC and AFCEC for each definable feature of work. The preparatory phase is a meeting before the work starts, once the required submittals are approved and copies are at the site. The initial phase checks the first segment of work as the crew starts. The follow-up phase is checking done daily until that feature is complete, recorded in the daily quality control report.
UFGS 01 32 01.00 10 Project Schedule
The Unified Facilities Guide Specification section used by USACE, NAVFAC and AFCEC for construction project schedules. It sets the scheduling settings to use (retained logic, longest path, physical percent complete, 8-hour days). It requires updates at least monthly, limits activity durations and bans leads and start-to-finish links. It requires a narrative report with each submission. It also sets how time impact analyses and time extension requests are prepared. Read the edition in your contract, since the section is revised.

Field planning and closeout

Certificate of occupancy
The building official's approval to occupy a building. A temporary certificate can let the owner move into finished areas while other work continues.
Closeout
The end of the job: punch list, final inspections, as-built drawings, warranties, spare parts data and final payment. Give each closeout submittal its own activity, so it gets tracked like any other work.
Commissioning
Testing that building systems work as designed, alone and together: HVAC, controls, fire alarm, emergency power. One system's test often waits on another's, so commissioning needs real logic in the schedule.
Daily report
The contractor's record of each workday: crews and hours by trade, equipment, work done, weather, deliveries, inspections and problems. Actual dates in the schedule should agree with it, and delay analysis leans on it heavily.
Last Planner System
A planning system promoted by the Lean Construction Institute. It puts near-term planning in the hands of the last planners: the people closest to the work with authority over it, usually foremen. It moves from milestone and pull planning, through make-ready work that clears constraints, to weekly commitments and daily check-ins. Percent plan complete tracks how reliably the commitments are kept, and the reasons for misses are reviewed.
Long-lead item
Equipment or material that takes months to design, approve, fabricate and ship, for example switchgear, generators, elevators or curtain wall. Give each one its own chain in the schedule: submittal, review, fabrication and delivery.
Look-ahead schedule
A short window of upcoming work, usually three or four weeks, pulled from the current update so the field can plan crews, deliveries and inspections. Pathizer's 6WLA Plan builds a six-week look-ahead from the analyzed network.
Make-ready planning
The Last Planner step that clears constraints before work reaches the weekly plan: submittals approved, RFIs answered, material on site, prior work done, crew available.
Percent plan complete (PPC)
The share of weekly commitments completed as promised: 32 done out of 40 committed is 80 percent. It measures how reliable the plan is. It says nothing about the job's position against the master schedule.
Phase
A part of the project that finishes at its own milestone, for example a building, a floor or an area turned over separately. Pathizer measures each phase against its milestone. The phase's total float (Phase TF) is the total float on that milestone. So delay and recovery are reported phase by phase, not only for the project finish.
Pull planning
Planning a phase backward from a milestone, with each trade saying what it needs handed over before it can start. The drywall crew, for example, states what it needs from MEP rough-in and the in-wall inspections before it can hang board.
Punch list
The list of work that is unfinished or does not meet the contract, made near the end of the job or of an area. Schedule punch work by area, because one bar at the end hides what holds up occupancy.
Request for information (RFI)
A written question from the contractor asking the designer to clarify the contract documents or fill a gap in them. Tie each open RFI to the activities waiting on it.
Shop drawings
Drawings from the contractor, a subcontractor or a supplier showing how something will be fabricated and installed, for example rebar placement or steel connections. Under FAR 52.236-21, approval does not relieve the contractor of errors in them.
Submittal
Information the contract requires for review before something is installed: shop drawings, product data, samples, test reports, certificates. Each has a review period, so schedule the submittal and its review ahead of procurement.
TCO (Temporary Certificate of Occupancy)
The building official's approval to occupy all or part of a building before every item is finished, once the life-safety work is done. Contracts often tie a milestone, and sometimes liquidated damages, to it. So the TCO date is usually a constrained finish milestone in the schedule and a common phase milestone.
Weekly work plan
The Last Planner level where foremen commit to specific tasks for the coming week, drawn only from work that is ready. Later they mark each one done or missed, with a reason.

Free scheduling and AI connectors

MCP (Model Context Protocol)
An open standard that lets an AI app call tools another program provides. A local MCP server runs on your own computer. P7 Free Scheduling's connector is one. It gives Claude Desktop, Claude Code or Codex tools to read and change the schedule open in your P7 tab. A remote MCP server runs online: Pathizer's Talk to your schedule connector is one, and it reads project results without editing schedules.
P7 Free Scheduling
Pathizer's free CPM scheduler at pathizer.com/p7. It runs in the browser with no account, in four windows (EPS, Projects, WBS and Activities). It has activities and relationships with lags, and F9 to schedule with total float and the critical path. It also has filters, layouts and a printed schedule report. It opens .XER and .XML schedule files and saves .XER. Schedules stay in the browser on your device, or in a folder you pick in Chrome or Edge, and are not uploaded to Pathizer. Through its local connector, your own Claude or Codex can build and edit the schedule, and P7 computes the dates.

Logic and constraints

As Late As Possible
A constraint that schedules an activity as late as it can go without delaying its successors, using up its free float. It suits deliveries timed just before installation. Because it consumes free float on purpose, a path can look tighter than its logic requires.
Dangling activity
An activity that has links, but on the wrong ends. If its only predecessor is finish-to-finish, nothing controls its start. If its only successor is start-to-start, nothing waits on its finish, so it can run long without moving anything. GAO's schedule guide calls this dangling logic.
Driving relationship
The predecessor link that actually sets an activity's early dates. An activity can have several predecessors, and usually only one controls when it can start. Scheduling software can flag that link as driving, and tracing driving links backward from the finish milestone shows the chain that controls completion. A non-driving predecessor still matters, because enough slip will make it the driver.
Finish On or Before
A soft constraint that sets a date the activity has to finish by. It affects late dates only, so when logic forecasts the work past the date, total float goes negative and the date itself stays put. That makes the lateness visible as a number, and USACE specifications use it on contractual interim completion dates for that reason.
Finish-to-finish (FF)
The successor cannot finish until the predecessor finishes. Fireproofing on a floor that cannot wrap up until steel erection on that floor finishes is a typical case. An activity whose only predecessor is FF has nothing controlling its start. So the scheduling engine can place that start as early as the data date.
Finish-to-start (FS)
The standard relationship: the successor cannot start until the predecessor finishes. Excavate the trench, then lay the pipe. Published DCMA guidance expects at least 90 percent of relationships to be finish-to-start.
Hard and soft constraints
A constraint pins an activity to a date, and logic does not place it. Mandatory Start and Mandatory Finish are the usual hard constraints. They override logic and can show work starting before its predecessors finish. Soft constraints (for example Start On or After and Finish On or Before) keep the logic intact but change dates or float. Use hard constraints only where a date is truly fixed.
Lag
A wait built into a relationship. On an FS link with a 7-day lag, the successor starts seven days after the predecessor finishes. The days count on the lag calendar set in the schedule options (predecessor, successor, 24-hour or project default). Seven days of cure on a 5-day calendar is more than a week. Keep lags for real waits like cure time, and model work as activities.
Lead (negative lag)
A negative lag, letting the successor start before the predecessor finishes. An FS link with a minus 5 day lag starts the successor five days before the predecessor ends. Leads are hard to status in the field and can distort total float and the critical path. A positive lag on a start-to-start link models the same overlap without a negative value.
Level of Effort (LOE)
An activity with no duration of its own that spans other work. It takes its dates from its predecessors and successors, so it stretches or shrinks as they move. Site supervision, project management and temporary facilities are the usual examples. Because its dates follow the work it spans, it cannot be constrained. In P7 Free Scheduling, Edit, Add Level of Effort over selection spans the selected activities.
Mandatory Start and Mandatory Finish
Hard constraints that fix an activity's early and late dates to the date entered, whatever the logic says. The schedule will show work starting before its predecessors finish if the date demands it. The float on the paths into and out of that activity is distorted. When one appears in an update, ask what real date it represents.
Milestone
A zero-duration activity marking a point in time, for example notice to proceed, dry-in, permanent power or substantial completion. Milestones carry no work or resources.
Open end
An activity missing a predecessor, a successor, or both. A sound network has two: the first activity (notice to proceed) with no predecessor and the last (project finish) with no successor. Any other open end makes the float around it mean little. An activity with no successor can slip for months without moving the finish date.
Precedence diagramming method (PDM)
The node-and-arrow form of CPM network behind XER and XML schedule files. Activities are boxes, relationships are arrows, and links come in four types (FS, SS, FF, SF), with or without lag.
Predecessor and successor
A predecessor has to happen before another activity can start or finish, and the successor is the activity waiting on it. Every activity except the first and last should have at least one of each.
Start On or After
A soft constraint that sets a date the activity cannot start before. It affects early dates only, and if logic already starts the work later, it does nothing. It suits real outside dates, for example the day the owner turns over a floor or the utility energizes permanent power.
Start-to-finish (SF)
The successor cannot finish until the predecessor starts. It is rare: temporary power that stays until permanent power is energized is the usual example. When an SF link turns up, check if two activities were linked in the wrong direction.
Start-to-start (SS)
The successor cannot start until the predecessor starts. It models overlapping work, for example drywall on level 2 starting a few days after framing on level 2 starts. An SS link usually carries a lag and is often paired with a finish-to-finish link. Without one, the follow-on trade can show finishing ahead of the work it depends on.

Schedule settings and updates

Activity code
A label attached to activities so they can be grouped, filtered and reported, for example area, floor, trade, phase or responsible subcontractor.
Activity type
The activity field that sets how an activity is scheduled. Task Dependent activities follow their own calendar, and Resource Dependent activities follow the calendars of their assigned resources. Start and Finish Milestones have zero duration. Level of Effort activities (for example project management) take their dates from their predecessors and successors and cannot be constrained. WBS Summary activities roll up the dates of everything under one WBS element.
Actual start and actual finish
The dates work really began and really ended, entered when the schedule is updated. Both have to fall on or before the data date, and they should match the daily reports.
Baseline schedule
The approved plan, saved as a frozen copy so later updates can be measured against it. Scheduling tools can keep more than one baseline per project, and the variance columns change depending on which one is assigned. Before comparing anything, confirm which baseline is assigned.
Calendar and hours per day
Every activity is assigned a calendar that sets its workdays, holidays and work hours. An XER file stores durations in hours, and the scheduling software converts them to days for display. An administrator option decides if it uses a global hours per day setting or each calendar's own. On a 10-hour calendar, a 30-hour activity shows as 3d with the calendar setting and as 3d6h with a global 8-hour setting. When a duration looks wrong, check the calendar before the logic.
Data date
The as-of date of a schedule update. Everything before it is actual progress, and everything after it is forecast.
Enterprise project structure (EPS)
The tree of folders that projects are filed under (for example company, region and program), above each project's own WBS. It decides where a project sits and how projects roll up together; the WBS breaks down the scope inside one project.
Original duration
The duration an activity was first estimated at, before any work was done. Compared with actual durations, it shows which kinds of work keep running long.
Out-of-sequence progress
Progress on an activity whose predecessors are not yet satisfied, for example roofing that started before the deck was finished. Retained logic and progress override give different dates for it. Usually the logic should be corrected to match how the work is really being built, or the reason for leaving it explained in the narrative.
Percent complete type
The activity setting that decides what percent complete means. Duration percent is calculated from original and remaining duration. Units percent comes from actual and remaining resource units. Physical percent is entered by the scheduler, or rolled up from activity steps, to reflect work in place. Duration percent only moves when remaining duration moves, so it can read 50 percent on work that has barely started.
Progress override
One of three scheduling options for out-of-sequence work, alongside retained logic and actual dates. It ignores the relationship once the successor has started, so the remaining work runs as if the predecessor were done. The schedule usually gets shorter, but it can show a sequence the crew cannot build, for example finishing roofing before the deck is complete. USACE specifications prohibit it, so check which option each update used.
Remaining duration
The working days left on an activity as of the data date. It equals the original duration before the activity starts and drops to zero when it finishes. In between, set it from the field. If the electrical foreman says the panel terminations need four more days, remaining duration is 4, whatever percent complete says.
Retained logic
A scheduling option for activities that started before their predecessors finished. The remaining work waits until the predecessors are complete. If roofing started before the deck under it was finished, the rest of the roofing is scheduled after the deck finishes. It is the conservative choice, because the dates still respect the original sequence.
Schedule log
The report the scheduling software writes when it schedules a project. Its warnings list activities without predecessors or successors, out-of-sequence activities and actual dates later than the data date. Read it after every recalculation.
Schedule narrative
A short written report that goes with each update. It explains what changed in the schedule and why: progress, the critical path, delays and what is being done about them.
Schedule revision
A change to the plan for remaining work: added or deleted activities, new logic, changed durations, calendars or constraints. An update records progress, and a revision changes the model. GAO's schedule guide treats them as separate steps, yet both often land in the same monthly file. So a finish date can move for reasons that have nothing to do with field progress.
Schedule update
Recording progress as of a new data date (actual dates, remaining durations, percent complete) and recalculating. List any revisions separately, so the reader can tell field progress from plan changes.
XER file
A tab-delimited schedule exchange file that carries the activity, relationship, calendar and status tables of a CPM schedule. Schedule updates are commonly shared and analyzed as XER files, one per data date.
XML schedule file
A schedule exchange file written in XML. Two kinds are common. One is the XML export of an enterprise scheduling database, which carries the projects, WBS, activities, relationships and calendars an XER file does. The other is Microsoft Project XML. The Free Schedule Viewer opens both, and P7 Free Scheduling imports either into a project it can schedule.