- Activity code
- A label attached to activities so they can be grouped, filtered and reported, for example area, floor, trade, phase or responsible subcontractor.
- Activity type
- The activity field that sets how an activity is scheduled. Task Dependent activities follow their own calendar, and Resource Dependent activities follow the calendars of their assigned resources. Start and Finish Milestones have zero duration. Level of Effort activities (for example project management) take their dates from their predecessors and successors and cannot be constrained. WBS Summary activities roll up the dates of everything under one WBS element.
- Actual start and actual finish
- The dates work really began and really ended, entered when the schedule is updated. Both have to fall on or before the data date, and they should match the daily reports.
- Baseline schedule
- The approved plan, saved as a frozen copy so later updates can be measured against it. Scheduling tools can keep more than one baseline per project, and the variance columns change depending on which one is assigned. Before comparing anything, confirm which baseline is assigned.
- Calendar and hours per day
- Every activity is assigned a calendar that sets its workdays, holidays and work hours. An XER file stores durations in hours, and the scheduling software converts them to days for display. An administrator option decides if it uses a global hours per day setting or each calendar's own. On a 10-hour calendar, a 30-hour activity shows as 3d with the calendar setting and as 3d6h with a global 8-hour setting. When a duration looks wrong, check the calendar before the logic.
- Data date
- The as-of date of a schedule update. Everything before it is actual progress, and everything after it is forecast.
- Enterprise project structure (EPS)
- The tree of folders that projects are filed under (for example company, region and program), above each project's own WBS. It decides where a project sits and how projects roll up together; the WBS breaks down the scope inside one project.
- Original duration
- The duration an activity was first estimated at, before any work was done. Compared with actual durations, it shows which kinds of work keep running long.
- Out-of-sequence progress
- Progress on an activity whose predecessors are not yet satisfied, for example roofing that started before the deck was finished. Retained logic and progress override give different dates for it. Usually the logic should be corrected to match how the work is really being built, or the reason for leaving it explained in the narrative.
- Percent complete type
- The activity setting that decides what percent complete means. Duration percent is calculated from original and remaining duration. Units percent comes from actual and remaining resource units. Physical percent is entered by the scheduler, or rolled up from activity steps, to reflect work in place. Duration percent only moves when remaining duration moves, so it can read 50 percent on work that has barely started.
- Progress override
- One of three scheduling options for out-of-sequence work, alongside retained logic and actual dates. It ignores the relationship once the successor has started, so the remaining work runs as if the predecessor were done. The schedule usually gets shorter, but it can show a sequence the crew cannot build, for example finishing roofing before the deck is complete. USACE specifications prohibit it, so check which option each update used.
- Remaining duration
- The working days left on an activity as of the data date. It equals the original duration before the activity starts and drops to zero when it finishes. In between, set it from the field. If the electrical foreman says the panel terminations need four more days, remaining duration is 4, whatever percent complete says.
- Retained logic
- A scheduling option for activities that started before their predecessors finished. The remaining work waits until the predecessors are complete. If roofing started before the deck under it was finished, the rest of the roofing is scheduled after the deck finishes. It is the conservative choice, because the dates still respect the original sequence.
- Schedule log
- The report the scheduling software writes when it schedules a project. Its warnings list activities without predecessors or successors, out-of-sequence activities and actual dates later than the data date. Read it after every recalculation.
- Schedule narrative
- A short written report that goes with each update. It explains what changed in the schedule and why: progress, the critical path, delays and what is being done about them.
- Schedule revision
- A change to the plan for remaining work: added or deleted activities, new logic, changed durations, calendars or constraints. An update records progress, and a revision changes the model. GAO's schedule guide treats them as separate steps, yet both often land in the same monthly file. So a finish date can move for reasons that have nothing to do with field progress.
- Schedule update
- Recording progress as of a new data date (actual dates, remaining durations, percent complete) and recalculating. List any revisions separately, so the reader can tell field progress from plan changes.
- XER file
- A tab-delimited schedule exchange file that carries the activity, relationship, calendar and status tables of a CPM schedule. Schedule updates are commonly shared and analyzed as XER files, one per data date.
- XML schedule file
- A schedule exchange file written in XML. Two kinds are common. One is the XML export of an enterprise scheduling database, which carries the projects, WBS, activities, relationships and calendars an XER file does. The other is Microsoft Project XML. The Free Schedule Viewer opens both, and P7 Free Scheduling imports either into a project it can schedule.