Product Roadmap

What is live in Pathizer today.

The five steps of each update period on the Flowchart and the delay analysis reports they build are live today. So are PDF Reports, P7 Free Scheduling, and the ChatGPT and Claude connector.

Live Today

Live features, in the order of the update cycle.

Controllers run each period on the Flowchart in six steps: Progress Entry, Add Fragnets, Health Check, Prepare for Review Meeting, Reporting, and Approve and distribute. The Flowchart shows the step each project is in, and a finished step can be reopened. The delay analysis and its reports are the record the cycle builds.

  1. Progress Entry

    Live today

    The field team enters progress once in the Schedule Updater, a working copy of the latest update. They enter it by a due date that moves on by the cycle (2 weeks or 1 month) when each new update arrives. Each edit saves as it is made, and a PDF progress update can fill it in. Send Final Update to Scheduler emails the .XER to the project's Controllers and locks the Updater. Controllers follow each project's step on the Flowchart, and a project past its due date shows red on the Projects page.

    • Update cycle and Flowchart
    • 6WLA Plan
    • Heatmap
  2. Add Fragnets

    Live today

    The Flowchart offers the Updater's .XER and can open it in P7. The scheduler and their AI add the period's time impacts there as fragnets under a Time Impact WBS: weather, RFIs, change orders and other events. Change orders are kept in the EOT Change Order register.

    • Added Activities / Fragnets
    • EOT Change Order / PCCO
  3. Health Check

    Live today

    A Controller drops one schedule file into the Health Check drop box on the Flowchart. Pathizer gives it the full Health Score as the would-be next update. It states findings about it, for example constraints, negative lags and each failed check. Pathizer does not edit the file: your own AI reads the findings through the connector, you decide, and the edits are made in P7. A Monte Carlo run can read the same file with the seed and settings of an earlier run, to compare before and after.

    • Health Score (DCMA-14)
    • Monte Carlo
  4. Prepare for Review Meeting

    Live today

    The team goes over the period's impacts and float paths, with someone driving P7 in its Float Paths layout. That layout bands the work by float path, in path order. The schedule views and the risk register are in Pathizer for the same meeting.

    • Schedule Explorer
    • Network Diagram
    • Risk Register (QAQC)
    • Production Simulator
  5. Reporting

    Live today

    A Controller drops the checked file into the Publish drop box, or publishes it from the Health Check. It goes into File Storage and the analysis starts by itself. Pathizer then drafts the schedule narrative and files the update's reports. A Controller signs them off and sends them to the team, and that opens the next period at Capture.

    • Executive schedule narratives
    • Report Generator
    • Project Dashboard
    • Executive Summary Report
    • Portfolio Dashboard
  6. Delay analysis

    Live today

    The record the cycle builds. After each analysis, Pathizer reads the full update history, with one active XER per data date. It files up to six ZIPs in the Delay Analysis folder of PDF Reports. Five are Concurrent Delay, Window Analysis (TIA), Performance (TIA), Continuous As-Is and Continuous Half-Step. The sixth is the Notice of Time Impact, with its Time Impact Schedule and float path reports. Each ZIP but the notice holds a Forensic Summary Report and the Half-Step and Void Review. The Performance (TIA) Report reads each update recalculated without its fragnets. Every figure traces back to the update it came from.

    • Half-Step Changes
    • Automated Window Analysis (TIA)
    • AACE MIP 3.1-3.9
    • Driver Gantt
    • Weather Days
    • Concurrency Window Analysis
    • Additive Window Analysis (TIA), after AACE 29R-03 MIP 3.7
    • Subtractive Analysis (TIA), after AACE 29R-03 MIP 3.9
    • Continuous As-Is, after AACE 29R-03 MIP 3.3
    • Continuous Half-Step, after AACE 29R-03 MIP 3.4
    • Forensic Summary Report
    • Forensic Review
  7. PDF Reports

    Live today

    The reports and schedule files Pathizer files for each update, in folders per project. You can open, download a file or a whole folder, rename, move, archive and search, with no storage size limit.

  8. Talk to your schedule

    Live today

    Connect ChatGPT or Claude to Pathizer through the OAuth MCP connector. It reads what you can see: your projects, the Health Score and the full Health Check with every DCMA check and the activities it flags. It also reads schedule narratives, delay analysis findings, Monte Carlo runs and the delay claim register. It gives 15 minute download links to a report or a whole folder. It can run and compare Monte Carlo simulations and put a file into the Health Check. It can draft a delay claim in your own conversation from the events and figures Pathizer recorded. It shows a preview before it creates, renames or archives a project, changes its address, or invites or changes team members. It also shows one before it uploads or removes a schedule update, starts an analysis, or changes Analysis Setup or the Updater due date. It makes the change only after your yes in the chat. Everything it does runs under your own Pathizer permissions.

  9. P7 Free Scheduling

    Live today

    A free CPM scheduler in the browser at pathizer.com/p7, with no sign-in. It has EPS, projects, WBS and activities, scheduling with F9, .XER and .XML import and .XER export. In Chrome and Edge, people who have the same project open in a shared folder see each other's changes, pointers and selections as they work. Baselines B1 to B3 draw as bars under each activity in the Gantt, with start, finish, duration and variance columns. The Schedule Report prints from any layout, on paper or to PDF. An optional local connector lets Claude or Codex build and edit the schedule, and can show a Pathizer Monte Carlo run as P7 columns.

This roadmap is directional and subject to change. It describes intended product direction, not a commitment to deliver any feature by any date. It should not be relied on in making purchasing decisions. Live capabilities are described on the product pages.

How The Numbers Are Produced

Calculated from the schedule, then drafted for review.

The analysis behind every live feature is calculated from your XER files, not generated. AI drafts narrative language only, and every draft is labelled for review.

Findings keep a link to the update they came from, so a figure in a narrative can be checked against the export behind it.