One project finish date hides the unit, line or area that is losing float.
Name each startup, completion or production milestone as a phase milestone. Each one is reported on its own: its float in every update and the activities on its driving path.
Pathizer for Industrial, Production & Mining
On a plant, a production line or a mine, the date that matters is mechanical completion, first power or first ore. Pathizer runs the monthly update cycle on your schedule file and shows what moved each of those milestones, and why.
No card to start.
Download Sample Update Report Made by Pathizer from a fictional sample project.
Behind Pathizer
Over a decade in project controls across a $3.5B+ portfolio at ENR 400 firms: residential, military, entertainment, healthcare, commercial, airport and data center work.
The Monthly Update
Outages, modules, tool installs, qualification and remote access move these schedules. The update cycle that records those moves is the same five steps every month, so each one is dated and traceable.
Progress Entry
The field team enters actual dates and remaining durations in the Schedule Updater, then sends the update to the scheduler as an .XER file.
Add Fragnets
The scheduler adds each time impact of the period as its own fragnet. Examples are scope found in a shutdown, a late module or a held permit.
Health Check
The revised file gets a Health Score and the DCMA 14-point checks before it is published. Duration changes since the last update show before anyone signs off.
Prepare for Review Meeting
The team walks the float paths into each startup or production milestone and decides what the next period protects.
Reporting
On Publish, Pathizer writes the narrative, files the reports and runs the delay analysis for each milestone you named.
The Problem, In Your Terms
One project finish date hides the unit, line or area that is losing float.
Name each startup, completion or production milestone as a phase milestone. Each one is reported on its own: its float in every update and the activities on its driving path.
Work found during a shutdown or a late module arrives in the next update with no date on it.
Each item goes in as its own fragnet, in the period it was found. The list of added work shows when it arrived. The delay analysis can count the days it pushed onto the path.
Shorter commissioning or qualification durations can hold a startup date on paper.
Half-Step Analysis keeps progress apart from revised durations and logic, so a date held by a re-forecast shows as a revision, not as work done.
What This Looks Like
In this illustrative chart, Phase D drops below zero float at UD01. It carries 21 days of negative float by UD07, and Phase A gains 11 days. On a plant those could be the mechanical completion of two units. A single project finish date would not show that split.
Illustrative analysis. Your results come from your own XER updates.
What You Walk Out With
Start with the update history of the unit or area whose startup date matters most.
How the monthly update worksQuestions
It works on the schedule file, not the industry. Pathizer reads .XER and .XML schedule files, Microsoft Project XML and SDEF. A plant, line or mine schedule in any of them goes through the same update cycle.
Yes. Name any activity as a phase milestone, such as mechanical completion of a unit, first power or first ore. Each one is reported on its own: its float in every update, its driving path and what moved it.
Each item is added as its own fragnet under a Time Impact WBS, in the period it was found. The Health Check scores the revised file before it is published. Later, the delay analysis can count the days that added work pushed onto the path.
It attributes a day to the party whose activities drove it, only where the schedule record supports it. The rest stays unattributed. It is not a determination of fault or entitlement.
30 days on your own projects for the whole organization, with the monthly update, the reports and delay analysis included. After the pilot it is $250 a month for every 2,500 activities, unlimited seats.
Files in a signed-in Pathizer workspace are not used to train public AI models.