On August 31, 2018, a little over three months before the planned December opening, Crossrail Ltd announced that the central section of the new railway under London would not open in December 2018. The reason it gave was a scheduling reason. The original programme for testing had been compressed, because contractors needed more time to finish fit-out in the central tunnels and to develop the railway systems software (TfL release, Aug 31, 2018).
Crossrail is the east to west railway now run as the Elizabeth line. It was authorized by the Crossrail Act 2008 (legislation.gov.uk) and delivered by Crossrail Ltd, with the Department for Transport and Transport for London as joint sponsors. The central section runs in new tunnels under the city, and Crossrail Ltd has described the project as bringing together multiple infrastructure contracts, new trains and three different signalling systems (TfL release, Aug 31, 2018).
The dates as published
The baseline came out of the 2010 Comprehensive Spending Review. The UK National Audit Office records £14.8 billion of funding agreed that year, including contingency, and December 2018 as the date announced in 2010 for starting services on the central section (NAO, Completing Crossrail, May 3, 2019). The same review moved full opening from May 2018 to December 2019 and cut costs partly by resequencing works.
| Announced | Central section opening | Who said it |
|---|
| 2010 | December 2018 | Sponsors and Crossrail Ltd, per NAO |
| Aug 31, 2018 | Autumn 2019 | Crossrail Ltd |
| Dec 10, 2018 | Autumn 2019 no longer committed | Crossrail Ltd, new CEO |
| Apr 25, 2019 | Six-month window, midpoint end of 2020 | Crossrail Ltd |
| Nov 8, 2019 | Not in 2020 | Crossrail Ltd |
| Jan 10, 2020 | Summer 2021 | Crossrail Ltd |
| Aug 21, 2020 | First half of 2022 | Crossrail Ltd |
| Actual | May 24, 2022 | TfL |
The funding moved with it. The government put the envelope at £15.4 billion in July 2018 (written statement, Jul 24, 2018) and at £17.6 billion in December 2018 (written statement, Dec 10, 2018). The NAO put the December 2020 funding package at £18.8 billion and a 2021 forecast at £18.9 billion, excluding the new trains and depot (NAO, Crossrail: a progress update, Jul 9, 2021). The Elizabeth line opened through central London on May 24, 2022 (TfL, May 24, 2022), and TfL described the full peak timetable on May 22, 2023 as the final milestone of the Crossrail project (TfL, May 22, 2023).
The reasons on record
Each announcement gave reasons, and they changed as the work did. In August 2018 it was compressed testing, tunnel fit-out and systems software. On December 10, 2018, the new chief executive, Mark Wild, said an autumn 2019 opening "could no longer be committed to at this stage," and the Mayor said the previous leadership had painted a far too optimistic picture (TfL release, Dec 10, 2018).
In April 2019 Crossrail Ltd published a plan built from "identifying and re-sequencing over 100,000 interdependent tasks," gave a six-month window instead of a date, and said Bond Street station was delayed because of design and delivery challenges (TfL release, Apr 25, 2019). The NAO read that window as some point between October 2020 and March 2021. In November 2019 the company named two critical paths: software for the signalling and train systems, and the assurance and handover process (Crossrail Ltd, Nov 8, 2019). In August 2020 it named the routeway, the stations and COVID-19 (Crossrail Ltd, Aug 21, 2020).
The auditors looked at how the plan itself was built. The NAO wrote that "Crossrail has been dominated by a fixed completion date of December 2018," that delivering by that date "meant multiple activities ran in parallel," and that Crossrail Ltd "did not have a sufficiently detailed delivery plan against which to track progress" until it began a bottom-up plan in late 2018 (NAO 2019, summary paragraphs 9, 10 and 12). The House of Commons Public Accounts Committee said the fixation on the December 2018 deadline led to warning signs being missed or ignored (PAC, HC 2004, Apr 3, 2019). A governance review by KPMG for the sponsors, dated January 23, 2019, recommended that sponsors pay close attention to trends in, and the level of, reported float in the programme (KPMG governance review).
Reading it as a scheduler
The part of this story that every scheduler has lived is the squeeze at the back end. When a finish date is fixed and the early work runs late, the late work gets shorter on paper. On a railway the late work is testing, integration and handover, and those are activities whose durations are hard to compress, because each test depends on the systems before it working first. The August 2018 announcement says this in its own words. Testing was compressed because the work ahead of it took longer.
Three changes between public updates are worth a scheduler's attention.
First, the form of the forecast changed. In April 2019 the date became a six-month window. That is a more honest way to state a forecast with real uncertainty in it, and it is also a signal that the team no longer trusted a single deterministic date. If your own owner or contractor switches from a date to a range, ask what risk analysis sits behind the range.
Second, the plan was rebuilt. Resequencing over 100,000 interdependent tasks is effectively a new baseline. After a rebuild like that, comparing new dates to the old plan activity by activity stops working, and the update should record the mapping between old and new logic so the history stays readable.
Third, the critical path moved off the construction work. By November 2019 both named critical paths were software and assurance. A schedule that models construction in detail and holds testing and handover as a few long bars will show plenty of float right up to the point where it suddenly has none. That fits the NAO's finding that the plan did not track progress in enough detail and KPMG's advice to watch the float trend, not just the date.
Were the reasons recorded? Yes, in every public announcement, and the auditors went further, into how the plan itself was built. What the public record cannot show is the float trend KPMG pointed to. The monthly float numbers sat inside the programme reports, and that is where a scheduler on a similar job should look first.
What to take from it
Crossrail is open and the project closed with the full timetable in 2023. The lessons that transfer are practical ones. Give testing, commissioning and handover real activities with real logic, not a single bar at the end. Report float on the driving path every month and plot it, because a date can hold steady while the float under it drains away. When the forecast becomes a range, say what produced the range. When the plan is rebuilt, keep the old and new versions side by side so the next reader can follow what changed.
Pathizer's Driver Gantt lines up the driving float path from every schedule update you load, sorted by finish date, so the float trend on your own job sits in one view instead of across a stack of monthly reports.
Sources
- TfL press release, central section to start in 2019, Aug 31, 2018. https://tfl.gov.uk/info-for/media/press-releases/2018/august/elizabeth-line-services-through-central-london-to-start-in-2019
- Crossrail Act 2008, legislation.gov.uk. https://www.legislation.gov.uk/ukpga/2008/18/introduction/enacted
- National Audit Office, Completing Crossrail, HC 2106, May 3, 2019. https://www.nao.org.uk/wp-content/uploads/2019/05/Completing-Crossrail.pdf
- UK government written statement, annual update on Crossrail, Jul 24, 2018. https://www.gov.uk/government/speeches/annual-update-on-crossrail-2018
- UK government written statement, Crossrail update, Dec 10, 2018. https://www.gov.uk/government/speeches/crossrail-update-10-december-2018
- National Audit Office, Crossrail: a progress update, HC 299, Jul 9, 2021. https://www.nao.org.uk/wp-content/uploads/2021/07/Crossrail-a-progress-update-2.pdf
- TfL press release, Elizabeth line opening, May 24, 2022. https://tfl.gov.uk/info-for/media/press-releases/2022/may/all-aboard-the-transformational-elizabeth-line
- TfL press release, full peak timetable, May 22, 2023. https://tfl.gov.uk/info-for/media/press-releases/2023/may/full-peak-elizabeth-line-timetable-introduced-as-railway-celebrates-remarkable-success-in-its-first-year
- TfL press release, new financing agreement, Dec 10, 2018. https://tfl.gov.uk/info-for/media/press-releases/2018/december/new-financing-agreement-confirmed-for-crossrail-proje
- TfL press release, plan to complete the Elizabeth line, Apr 25, 2019. https://tfl.gov.uk/info-for/media/press-releases/2019/april/crossrail-ltd-outlines-plan-to-complete-the-elizabeth-line
- Crossrail Ltd, update on progress, Nov 8, 2019. https://www.crossrail.co.uk/news/articles/update-on-progress-to-complete-the-elizabeth-line-1
- Crossrail Ltd, summer 2021 announcement, Jan 10, 2020. https://www.crossrail.co.uk/news/articles/elizabeth-line-services-through-central-london-expected-to-commence-in-summer-2021
- Crossrail Ltd, update following the August 2020 board, Aug 21, 2020. https://www.crossrail.co.uk/news/articles/update-following-crossrail-board-august-2020
- House of Commons Public Accounts Committee, Crossrail: progress review, HC 2004, Apr 3, 2019. https://publications.parliament.uk/pa/cm201719/cmselect/cmpubacc/2004/2004.pdf
- KPMG, Independent review of Crossrail, Governance, Jan 23, 2019, published by TfL. https://tfl.gov.uk/cdn/static/cms/documents/governance-redacted.pdf
Try it on your own files
Open your latest schedule update. Add last month's to see what changed. The free tools need no account. They are a screening, a first look before a full review.