Megaprojects

Honolulu's Skyline rail, read through the schedule

As of

Line drawing of an elevated rail guideway with a launching gantry and palms, and a hand holding a schedule tablet
Illustrative rendering, not a photo of the project

In July 2026 the head of the Honolulu Authority for Rapid Transportation called the current plan "our no float schedule," with about 100 days of flexibility left as a cushion, while the Federal Transit Administration's monitor put a 65 percent chance on the last segment opening in the spring of 2032 instead of March 31, 2031 (Honolulu Civil Beat, Jul 26, 2026). Those two lines, side by side, are the current state of a schedule that has been rebuilt several times since 2008.

Skyline is a grade-separated rail line on Oahu, built by the Honolulu Authority for Rapid Transportation (HART) and operated by the City and County of Honolulu. It opens in segments. The first segment, nearly eleven miles from East Kapolei to Halawa, opened on June 30, 2023 (City DTS, Jun 16, 2023). The second added five miles and four stations on October 16, 2025 (City DTS, Oct 15, 2025). The third, three miles and six stations to the Civic Center, is the one now in question.

The dates as published

Voters approved rail 53 percent to 47 percent on November 4, 2008 (Honolulu Advertiser, Nov 10, 2008). The original plan was a 21-station line to Ala Moana Center in 2019, as the Star-Advertiser later summarized it (Star-Advertiser, Jun 25, 2023). The federal grant agreement was signed on December 19, 2012, and the Hawaii State Auditor later summarized the commitment: the City pledged to complete the project by 2020 for $5.122 billion, with a fixed federal share of $1.55 billion (State Auditor Report 19-03, Jan 2019).

WhenCostFull line openingSource
Dec 2012 grant agreement$5.122B2020 (revenue service Jan 31, 2020)State Auditor 19-03
2016$6.83B2022State Auditor 19-03
Sep 2017 recovery plan$8.165BDec 2025State Auditor 19-03
2018, FTA recommended$9.188BSep 2026State Auditor 19-03
Mar 2021$12.4BRevenue service Mar 2031Hawaii News Now
May 2022, shortened line$9.93B2031, ending at Civic CenterCivil Beat
Feb 2024 amended grant agreement$9,933,034,332Mar 31, 2031Amended agreement
Jul 2026, FTA monitorLast segment spring 2032, 65 percent confidenceCivil Beat

The 2022 change was a scope cut. The line now ends at the Civic Center instead of Ala Moana Center, and the FTA accepted the amended recovery plan on September 30, 2022. The amended grant agreement describes an 18.9-mile line from East Kapolei to the Civic Center with a revenue service date of March 31, 2031, and states that the baseline schedule "is not to be modified because it is to be used as a basis for comparing planned to actual" (amended grant agreement).

The reasons on record

The State Auditor's 2019 report found that the opening date had been pushed back six times, from March 2019 to December 2025. It traced part of the early slip to sequencing. The first guideway contract, worth $483 million, was signed in November 2009, but utility relocation did not break ground until February 2011, more than 15 months later, and delay change orders reached a 22 percent premium over the original award. The same report quoted a 2015 FTA letter that gave the then-current date "only an eight percent probability" of being met, and found that HART reported information to the public that "often contradicted its own internal projections or differed from what it was telling the FTA" (State Auditor 19-03).

The courts stopped work once. In August 2012 the Hawaii Supreme Court held in Kaleikini v. Yoshioka that the City erred by starting construction before the historic preservation review was complete (Hawaii Supreme Court opinion). The Auditor reports that construction resumed in September 2013.

For the current segment, the reasons are utilities and foundations. Civil Beat reported in November 2023 that federal reports put the Dillingham Boulevard utility relocation on the critical path to March 2031 (Civil Beat, Nov 13, 2023). HART's April 2026 presentation anticipated that relocation finishing by the end of 2026, and construction of the downtown guideway and stations finishing in 2030 (HART presentation, Apr 17, 2026). In July 2026 Civil Beat attributed the monitor's projected delay to design and construction problems, including delayed downtown utility contracts and problems drilling shafts for the rail supports.

Reading it as a scheduler

The amended grant agreement gives a scheduler something useful: a planned milestone table to hold the work against. HART's projections in it put Segment 2 complete in June 2025; Segment 2 opened October 16, 2025. They put the fourth utility relocation package complete in February 2026; HART's April 2026 presentation said the end of 2026. The agreement also fixes the baseline in place, which keeps planned and actual comparable. It also means the useful record now lives in the updates, and each update has to explain its own movement against that fixed plan.

The phrase "no float schedule" with 100 days of flexibility is worth stopping on. If the logic path to March 31, 2031 has no float, the 100 days have to sit somewhere else, for example as a contingency held outside the activity logic, or as a gap between the planned finish and the commitment date. The public record does not say which, and either is a reasonable way to run a job. A reader needs to know which, because 100 days of contingency and 100 days of float behave differently when the next delay arrives.

Then there are the two forecasts. HART targets March 31, 2031. The monitor's analysis gives 65 percent confidence in spring 2032. These answer different questions. One is a deterministic target; the other is a probability from a risk analysis. A clean update reports both and says which one the team is managing to.

The Auditor's 2019 finding about public reporting is the general lesson. Whatever the right forecast is, there should be one per update, and the same one should go to the board, the funder and the public.

What to watch next

Watch the Dillingham utility relocation against its end of 2026 completion, since federal reports have tied it to the critical path. Watch whether HART's March 31, 2031 target moves in the next recovery plan update, and whether the 100 days of flexibility is reported again as a number. The next FTA monitoring report will show whether the spring 2032 projection firms up or recovers.

Pathizer derives a schedule risk register from each analyzed schedule update, flagging float erosion and consecutive slips, so on your own job a shrinking cushion shows up as it shrinks.

Sources

  1. Honolulu Civil Beat, Kevin Dayton, another delay for Honolulu rail, Jul 26, 2026. https://www.civilbeat.org/2026/07/another-delay-for-honolulu-rail-the-timeline-appears-to-be-slipping-again/
  2. City and County of Honolulu, Department of Transportation Services, Segment 1 opening, Jun 16, 2023. https://www.honolulu.gov/dts/?p=8145
  3. City and County of Honolulu, Department of Transportation Services, Segment 2 begins passenger service, Oct 15, 2025. https://www.honolulu.gov/dts/skyline-segment-2-begins-passenger-service-tomorrow-october-16-2025/
  4. Honolulu Advertiser, vote result, Nov 10, 2008. https://honoluluadvertiser.com/article/2008/Nov/10/ln/hawaii811100345.html
  5. Honolulu Star-Advertiser, Skyline rolls out after years of delays, Jun 25, 2023. https://www.staradvertiser.com/2023/06/25/hawaii-news/skyline-honolulu-rail-rolls-out-after-years-of-delays-cost-overruns/
  6. Hawaii State Auditor, Report 19-03, Jan 2019. https://files.hawaii.gov/auditor/Reports/2019/19-03.pdf
  7. Hawaii News Now, cost of rail rises, Mar 18, 2021. https://www.hawaiinewsnow.com/2021/03/19/cost-rail-rises-b-passengers-may-be-able-board-march
  8. Honolulu Civil Beat, HART board approves a shorter route, May 6, 2022. https://www.civilbeat.org/2022/05/hart-board-approves-a-new-honolulu-rail-plan-for-a-shorter-route
  9. Amended Full Funding Grant Agreement, HART (DocumentCloud copy). https://s3.documentcloud.org/documents/24176379/amended-ffga-hart.pdf
  10. HART, FTA approves recovery plan. https://honolulutransit.org/fta-approves-hart-recovery-plan/
  11. HART, amended grant agreement signed, Feb 2, 2024. https://honolulutransit.org/honolulu-and-hart-sign-amended-full-funding-grant-20240202/
  12. Hawaii Supreme Court, Kaleikini v. Yoshioka, Aug 24, 2012. https://www.courts.state.hi.us/docs/opin_ord/sct/2012/aug/SCAP-11-0000611ada.pdf
  13. Honolulu Civil Beat, high likelihood of more delays, Nov 13, 2023. https://www.civilbeat.org/2023/11/high-likelihood-of-more-delays-in-critically-important-honolulu-rail-work
  14. HART presentation to the State TOD Council, Apr 17, 2026. https://files.hawaii.gov/dbedt/op/lud/01TODCMTG/20260417/03-HARTPresentation.final.pdf

Try it on your own files

Open your latest schedule update. Add last month's to see what changed. The free tools need no account. They are a screening, a first look before a full review.