On October 8, 2026, the Gateway Development Commission announced that the first tunnel boring machine on the Hudson Tunnel Project "has begun mining on schedule" (GDC release, Oct 8, 2026). Ten months earlier the Commission had said the first machine would start boring in the spring and the second in the summer (GDC release, Dec 15, 2025). Both statements can be true at once, and working out how is a good exercise in reading a public schedule.
The project builds a new rail tunnel, in two tubes, under the Hudson River between New Jersey and Manhattan, then rehabilitates the existing North River Tunnel, which was inundated with seawater during Superstorm Sandy in 2012 (GDC release, May 28, 2021). The Gateway Development Commission (GDC) is the project sponsor, with Amtrak leading three of the construction packages (Amtrak OIG, Dec 15, 2025) and the Federal Transit Administration funding and overseeing it.
The dates as published
The project has two kinds of finish date in its public record. GDC's own statements give 2035 for the new tunnel and 2038 for the finished rehabilitation. FTA's project profile and oversight reports give November 2040 for the project as a whole.
| When | What was said | Source |
|---|
| Jun 2016 | Both tunnels in service by 2028 | FTA project profile |
| Nov 2017 | In service by 2030 | FTA project profile |
| Nov 2019 | In service by 2029 | FTA project profile |
| Nov 2021 | In service by 2035 | FTA project profile, FY24 |
| Aug 31, 2022 | $16.1 billion; new tunnel 2035, project 2038 | GDC release |
| Jul 8, 2024 | Grant agreement signed for $6.88 billion; 2035 and 2038 | GDC release |
| Jul 2024 | Project estimated complete November 2040 | FTA profile, FY25 |
| Jun 2025 | Construction began Oct 2023, expected to finish Nov 2040; $16.041 billion including finance charges | FTA monitoring report |
Sources for each row are listed at the end. The environmental review also slipped before construction began. In August 2020 GDC noted that the federal permitting dashboard had targeted March 30, 2018 for the final environmental impact statement and record of decision (GDC release, Aug 28, 2020). Both were issued in May 2021. GDC's 2022 cost update listed "increased schedule contingencies based on Federal risk analysis methodology" among the drivers of the $16.1 billion estimate (GDC release, Aug 31, 2022).
The packages and the tunnel boring start
The work is split into separate construction contracts. GDC's public statements on the start of tunnel boring read like this:
| GDC statement | Start of tunnel boring |
|---|
| Dec 12, 2024 | Machines to dig the New Jersey section "in 2026"; the same release also said tunnel boring would begin "next year" |
| May 20, 2025 | Expected to begin in 2026 |
| Dec 15, 2025 | First machine in the spring, second in the summer |
| Oct 8, 2026 | First machine began mining "on schedule"; second to launch "in the coming weeks" |
The Palisades Tunnel contract, awarded in August 2024 for $465 million, carries substantial completion by September 2, 2027 in FTA's June 2025 monitoring report (FTA, Jun 2025). The first two machines are building the first 5,100 feet of the tunnel tubes, from the portal in North Bergen to the Hudson County access shaft, and GDC expects about 30 feet of tunnel a day and about a year for that stretch. The Manhattan Tunnel contract was awarded in February 2025 for $1.18 billion with substantial completion anticipated in 2029. The Hudson River Tunnel contract, which had been scheduled for award in late 2025 or early 2026, was awarded on April 27, 2026 for $1.29 billion.
Two smaller packages show how the same work can be described two ways. FTA's December 2024 monitoring report gave the Tonnelle Avenue bridge a forecast substantial completion of October 31, 2025, against a baseline of October 12, 2025; GDC later said it was substantially complete in late 2025. On the Amtrak-led Hudson Yards concrete casing, the same FTA report said the contractor's schedule update showed substantial completion "158 calendar days behind schedule," while GDC said in May 2025 that the section had reached its halfway point on schedule and on budget (FTA, Dec 2024). These measure different things, and the public record does not reconcile them.
The funding pause
On September 30, 2025, FTA paused grant disbursements pending a review of GDC's Disadvantaged Business Enterprise program, and the next day all federal funding was paused, according to GDC (GDC release, Jan 27, 2026). GDC suspended construction on February 6, 2026 (GDC release, Feb 6, 2026) and said construction was resuming the week of February 24, with the tunnel and surface alignment procurements on hold (GDC release, Feb 24, 2026). E&E News reported a June 29, 2026 ruling that the freeze was contrary to law insofar as it suspended disbursements, and the New Jersey Monitor reported in September that the parties agreed to dismiss the appeal.
Reading it as a scheduler
Start with the two finish dates. A 2035 in-service date and a November 2040 project completion can both be correct if they measure different things: one a revenue milestone, the other the end of all work, possibly with contingency or closeout included. The public documents do not say which, and that is the first question to ask. Any reader comparing this project to another needs to know whether the date they are quoting carries schedule contingency.
Then look at "on schedule." When GDC says the October 2026 start was on schedule, the natural reading is that it met the current baseline for that package. The December 2025 forecast was spring for the first machine and summer for the second. Between those statements sit a construction suspension and a court case, and the public record does not say whether the package baseline was revised. On your own job, a forecast that moves and then lands "on schedule" should come with a note showing which baseline it was measured against. The December 2024 release is a smaller lesson of its own: one document gave two different years for the same start, and a reader quoting either one would be quoting GDC accurately.
The Hudson Yards casing is the same question at package level. A contractor update 158 days behind and an owner statement of on schedule can describe a forecast against a contract date and progress against a budget. Both belong in the record, with the measure named.
Finally, the funding pause. A suspension from February 6 to the week of February 24, 2026, plus procurements on hold, is a discrete event with a start and an end. In a CPM schedule it should show up as its own activities on each affected package, with the reason recorded in the update where it happened. If it is folded into longer remaining durations instead, the time is still lost, but nobody can point to where it went.
What to watch next
GDC said a second tunnel boring machine would launch in the coming weeks. Watch its actual start date and the advance rate against the stated 30 feet a day. Watch the Hudson River ground stabilization work, which FTA reported at a January 20, 2027 substantial completion date, and the Palisades Tunnel against September 2, 2027. The next FTA quarterly monitoring report is the place to check whether the November 2040 completion still holds and whether the risk register is published in full; the June 2025 report noted the revised complete register was not included.
Pathizer compares each schedule update with the one before it and lists the activities added between them, so a suspension or a re-forecast shows up as its own change rather than disappearing into the next baseline.
Sources
- Gateway Development Commission, first tunnel boring machine begins mining, Oct 8, 2026. https://www.gatewayprogram.org/wp-content/uploads/2026/10/TBM-Start-of-Mining-Press-Release.pdf
- Gateway Development Commission, Final EIS and Record of Decision, May 28, 2021. https://www.gatewayprogram.org/wp-content/uploads/2025/10/2021-05-28-Hudson-Tunnel-Project-ROD.pdf
- FTA project profile, June 2016. https://www.transit.dot.gov/sites/fta.dot.gov/files/docs/NJ-NY%20Hudson%20Tunnel%20PD%20Profile_0.pdf
- FTA project profiles, November 2017 and November 2019 ratings, read through Wayback Machine copies, FTA Capital Investment Grants project 130166. https://www.transit.dot.gov/funding/grant-programs/capital-investments
- FTA project profile, FY24. https://www.transit.dot.gov/sites/fta.dot.gov/files/2023-03/NJ-NY-Hudson-Tunnel-Project-Profile-FY24_0.pdf
- Gateway Development Commission, cost and schedule update, Aug 31, 2022. https://www.gatewayprogram.org/wp-content/uploads/2025/10/GDC-Release-Hudson-Tunnel-Project-Cost-Schedule.pdf
- Gateway Development Commission, Full Funding Grant Agreement signed, Jul 8, 2024. https://www.gatewayprogram.org/wp-content/uploads/2025/10/GDC-FFGA-Signing-Press-Release-7.8.24_PROOFEDfin-1.pdf
- FTA project profile, FY25. https://www.transit.dot.gov/sites/fta.dot.gov/files/2024-09/NJ-NY-Hudson-Tunnel-Project-Profile-FY25.pdf
- FTA quarterly monitoring report, June 2025. https://www.transit.dot.gov/sites/fta.dot.gov/files/2025-10/Quarterly-Monitoring-Report-NJ-NY-Hudson-Tunnel-Project-June-2025_0.pdf
- FTA quarterly monitoring report, December 2024. https://www.transit.dot.gov/sites/fta.dot.gov/files/2025-10/Quarterly-Monitoring-Report-NJ-NY-Hudson-Tunnel-Project-December-2024_0.pdf
- Gateway Development Commission, financial plan release, Aug 28, 2020. https://www.gatewayprogram.org/wp-content/uploads/2025/10/GDC-20-08-23_HTP-FinancialPlan-PR-1.pdf
- Gateway Development Commission, Tonnelle Avenue more than 50 percent complete, Dec 12, 2024. https://www.gatewayprogram.org/wp-content/uploads/2025/10/GDC-Tonnelle-Ave-50-Percent-Completion-Release-for-Website.pdf
- Gateway Development Commission, May 2025 board meeting release, May 20, 2025. https://www.gatewayprogram.org/wp-content/uploads/2025/10/5.20.2025-May-Board-Meeting-Press-Release-for-website.pdf
- Gateway Development Commission, December 2025 board meeting release, Dec 15, 2025. https://www.gatewayprogram.org/wp-content/uploads/2025/12/GDC-December-Board-Meeting-Press-Release-for-website.pdf
- Gateway Development Commission, Manhattan Tunnel award, Feb 3, 2025. https://www.gatewayprogram.org/wp-content/uploads/2025/10/GDC-February-3-2025-Board-Meeting-Press-Release-for-website.pdf
- Gateway Development Commission, Hudson River Tunnel award, Apr 27, 2026. https://www.gatewayprogram.org/wp-content/uploads/2026/04/P1C-Contract-Award-Press-Release.pdf
- Gateway Development Commission, January 2026 board meeting release, Jan 27, 2026. https://www.gatewayprogram.org/wp-content/uploads/2026/01/01.27.2026-Board-Meeting-Press-Release-for-Website.pdf
- Gateway Development Commission, construction pause, Feb 6, 2026. https://www.gatewayprogram.org/wp-content/uploads/2026/02/Construction-Pause-Press-Release-Feb-6-2026.pdf
- Gateway Development Commission, construction update, Feb 24, 2026. https://www.gatewayprogram.org/wp-content/uploads/2026/02/GDC-Release-Feb-24-2026-Construction-Update-for-Website.pdf
- E&E News, judge rules on Gateway funding freeze, Jun 30, 2026. https://www.eenews.net/articles/judge-rules-trump-admin-acted-contrary-to-law-in-freezing-gateway-tunnel-money/
- New Jersey Monitor, appeal on Gateway funding, Sep 18, 2026. https://newjerseymonitor.com/2026/09/18/trump-appeal-gateway-tunnel-funding/
- Amtrak Office of Inspector General, OIG-A-2026-001, Hudson Tunnel Project, Dec 15, 2025. https://www.oversight.gov/sites/default/files/documents/reports/2025-12/OIG-A-2026-001_Hudson%20Tunnel%20Project%20%28REDACTED%29.pdf
- Gateway Development Commission, August 1, 2024 board meeting release (Palisades Tunnel award). https://www.gatewayprogram.org/wp-content/uploads/2025/10/GDC-August-1-Board-Meeting-Release-for-Website.pdf
Try it on your own files
Open your latest schedule update. Add last month's to see what changed. The free tools need no account. They are a screening, a first look before a full review.