In the July 2020 update of the Vogtle Unit 3 schedule, there were 2 hard constraints. A few months earlier there had been 141. By the end of August 2020 there were 121 again. Those counts come from sworn testimony by the Georgia Public Service Commission's own staff (Roetger and Jacobs, PSC Docket 29849, Nov 24, 2020), and they say more about how this job was scheduled than any cost headline.
Vogtle Units 3 and 4 are two Westinghouse AP1000 reactors built next to the two existing units at Plant Vogtle near Waynesboro, Georgia. Georgia Power owns 45.7 percent of the new units (AP via GPB, Dec 19, 2023) and reported on them to the Commission in a semi-annual Vogtle Construction Monitoring docket. Each round, the company filed a report and the PSC staff and an independent monitor filed testimony on it, which is why the public record goes inside the schedule and not only around it.
The dates as published
The Commission certified construction on March 17, 2009, with Georgia Power's share at an in-service cost of about $6.4 billion including financing (Georgia Power 8-K, Mar 17, 2009). The AP later summarized the starting point as $14 billion for the project and completion by 2017 (AP via GPB, Dec 19, 2023). The engineering, procurement and construction contract carried guaranteed substantial completion dates of April 2016 and April 2017 (Southern Company 8-K, Jan 29, 2015). The NRC issued the combined licenses on February 10, 2012 (Federal Register, Feb 29, 2012).
From there the commercial operation targets moved like this. Each row is a public filing or release, and the reason column is the company's own wording.
| Announced | Unit 3 | Unit 4 | Reason the company gave |
|---|
| Jan 29, 2015 | Q2 2019 | Q2 2020 | Contractor's revised forecast, an 18 month shift |
| Aug 31, 2017 | Nov 2021 | Nov 2022 | Recommendation to finish after Westinghouse's bankruptcy |
| Jul 29, 2021 | Q2 2022 | Q1 2023 | Productivity, remediation, pace of system turnovers |
| Oct 21, 2021 | Q3 2022 | Q2 2023 | Electrical installation and remediation on Unit 3 |
| Feb 17, 2022 | Q4 2022 or Q1 2023 | Q3 or Q4 2023 | Completing work packages, including inspection records |
| Jan 11, 2023 | Apr 2023 | | Vibration in cooling system piping |
| Jun 16, 2023 | Jul 2023 | | Degraded hydrogen seal in the main generator |
| Oct 2023 | | Q1 2024 | Motor fault in a reactor coolant pump |
| Actual | Jul 31, 2023 | Apr 29, 2024 | |
Sources for the table are listed at the end, one per row. The 2017 dates came after Westinghouse filed for Chapter 11 on March 29, 2017 (Southern Company 10-K FY2017). Georgia Power then recommended finishing the project with Southern Nuclear in charge and Bechtel running day-to-day construction, at a Georgia Power share of about $8.8 billion and a total near $19 billion (Georgia Power release, Aug 31, 2017). The Commission voted unanimously in December 2017 to continue (Georgia PSC, 2017 releases).
In April 2020 the company cut the site workforce by about 20 percent for COVID (8-K, Apr 16, 2020), and later filings said the pandemic consumed about three to four months of schedule margin. In 2021 alone the dates were revised several times; the October 2021 release called its change "a three-month shift for each unit" (Georgia Power, Oct 21, 2021). Unit 3 entered commercial operation on July 31, 2023 and Unit 4 on April 29, 2024 (Unit 3 release, Unit 4 release). The AP reported the owners' projected cost at $31 billion, nearing $35 billion with what Westinghouse paid (AP via Power Engineering, Apr 29, 2024).
What the monitors said about the schedule itself
The dates tell part of the story. The PSC staff testimony went inside the integrated project schedule, and that is where a scheduler should spend time.
In November 2019, staff witnesses Steven Roetger and William Jacobs wrote that the schedule assumptions, including unit rates, were "from the outset, unrealistic and unachievable" (PSC staff testimony, Nov 22, 2019). The same testimony explained that what the project called "management time" is what most of us would call schedule float.
A year later the same witnesses described the July 2020 update. The Unit 3 schedule had been eased, and staff said "all but approximately 30 days" of management time was removed. Hard constraints dropped from 141 to 2 as of a June 27, 2020 data date. By the end of August the count was back to 121, and staff explained why in plain terms: as adherence slipped, the project team "was forced to hard constrain precursor activities that led to the major milestones" (PSC staff testimony, Nov 24, 2020).
The independent monitor, Don Grace of the Vogtle Monitoring Group, filed the same day and reported a downward adjustment of 54,000 earned hours because earned hours had been over-reported, which turned a position of about two weeks ahead into about two weeks behind (Grace testimony, Nov 24, 2020). These are the positions of the Commission's staff and its monitor. The company's own filings in the same docket give its side, and nothing here is a finding of fault by anyone.
Reading it as a scheduler
Three things moved on this job between public updates, and only one of them is the finish date.
The first is constraints. A hard constraint in a CPM schedule, such as a Mandatory Finish, tells the software to hold a date whatever the logic says. With 2 of them, the Unit 3 dates were being driven by logic and durations. With 121, a good part of the near-term path was being held in place by hand. The float you read off that schedule is the gap between a forecast and a date someone typed, so it stops telling you how much room the work really has. The staff testimony is useful because it recorded both the count and the reason for it.
The second is float, under a different name. Removing all but about 30 days of management time in one update is a large decision, and the record shows it happened in a revision rather than through progress. When float leaves a schedule by revision, the update narrative should say so, because otherwise the next slip looks like a performance problem when part of it was a planning choice.
The third is the progress measure. A 54,000 hour correction to earned hours changes what every schedule performance number before it meant. Georgia Power's 2019 monitoring report also defined its SPI so that a value above 1.0 meant fewer hours earned than planned (VCM 20/21 report, Aug 2019), which is the reverse of the usual earned value convention. Anyone comparing that index to another project would get the direction wrong unless they read the definition first.
Were the reasons recorded? For the date changes, mostly yes. Every move in the table above came with a stated cause in an SEC filing or release. For the changes inside the schedule, the reasons are on the record only because the Commission's staff dug them out and put them in testimony.
What to take from it
Vogtle is finished, so there is no next update to watch. The habits carry over to any job with a contract date that cannot move.
Count hard constraints in every update and write down why each new one was added. A rising count with a steady finish date is a signal worth a sentence in the narrative. Track float as float, whatever the project calls it, and note when a revision removes it. Check how the progress index is defined before trusting its direction. When earned quantities get corrected, restate the earlier periods or at least flag them, so the trend line does not quietly change meaning.
Pathizer runs the DCMA 14-point checks, hard constraints included, on each schedule update you load, so a count that jumps from one update to the next shows up in the update where it happened.
Sources
- Georgia Power Form 8-K, PSC certification, Mar 17, 2009. https://www.sec.gov/Archives/edgar/data/41091/000009212209000023/soga8k3-09.htm
- AP via GPB, PSC rate decision, Dec 19, 2023. https://www.gpb.org/node/1037096
- Southern Company 8-K, revised schedule, Jan 29, 2015. https://www.sec.gov/Archives/edgar/data/92122/000009212215000004/ga-so8xkvgtlschedule1x15.htm
- Federal Register, Vogtle 3 and 4 combined licenses, Feb 29, 2012. https://www.govinfo.gov/content/pkg/FR-2012-02-29/html/2012-4824.htm
- Southern Company 10-K FY2017, Note on Vogtle (Westinghouse bankruptcy, Bechtel). https://www.sec.gov/Archives/edgar/data/92122/000009212218000012/R16.htm
- Georgia Power release, recommendation to complete, Aug 31, 2017. https://southerncompany.mediaroom.com/2017-08-31-Georgia-Power-files-recommendation-to-complete-construction-of-Vogtle-nuclear-expansion
- Georgia PSC, 2017 news releases (Dec 21, 2017 decision). https://psc.ga.gov/newsroom/newsreleases/2017-news-releases/
- Southern Company 8-K, COVID workforce reduction, Apr 16, 2020. https://www.sec.gov/Archives/edgar/data/92122/000009212220000038/soga8-kvogstatus4x20.htm
- Southern Company 10-Q Q2 2021 (Jul 29, 2021 dates). https://www.sec.gov/Archives/edgar/data/92122/000009212221000064/R13.htm
- Georgia Power release, schedule adjustment, Oct 21, 2021. https://southerncompany.mediaroom.com/2021-10-21-Georgia-Power-adjusts-schedule-for-Vogtle-units-3-4
- Southern Company 10-K FY2021 (Feb 17, 2022 dates). https://www.sec.gov/Archives/edgar/data/92122/000009212222000003/R54.htm
- Southern Company 8-K, Jan 11, 2023. https://www.sec.gov/Archives/edgar/data/92122/000009212223000004/so-20230111.htm
- Southern Company 8-K, Jun 16, 2023. https://www.sec.gov/Archives/edgar/data/92122/000009212223000058/so-20230616.htm
- Southern Company 8-K, Oct 2023 (Unit 4 reactor coolant pump). https://www.sec.gov/Archives/edgar/data/92122/000009212223000095/so-20231005.htm
- Georgia Power, Unit 3 commercial operation, Jul 31, 2023. https://southerncompany.mediaroom.com/2023-07-31-Vogtle-Unit-3-goes-into-operation
- Georgia Power, Unit 4 commercial operation, Apr 29, 2024. https://southerncompany.mediaroom.com/2024-04-29-Vogtle-Unit-4-enters-commercial-operation
- AP via Power Engineering, Unit 4 online, Apr 29, 2024. https://www.power-eng.com/nuclear/plant-vogtle-unit-4-is-now-online/
- Georgia PSC staff testimony (Roetger, Jacobs), Docket 29849, Nov 22, 2019. https://services.psc.ga.gov/api/v1/External/Public/Get/Document/DownloadFile/178972/61791
- Georgia PSC staff testimony (Roetger, Jacobs), Docket 29849, Nov 24, 2020. https://services.psc.ga.gov/api/v1/External/Public/Get/Document/DownloadFile/183341/65219
- Independent monitor testimony (Grace), Docket 29849, Nov 24, 2020. https://services.psc.ga.gov/api/v1/External/Public/Get/Document/DownloadFile/183339/65215
- Georgia Power VCM 20/21 report, Aug 2019. https://services.psc.ga.gov/api/v1/External/Public/Get/Document/DownloadFile/178224/61059