Why a project finish date hides phase risk
A building handed over in phases has several dates that matter. One is a turnover to the owner's tenant. Others are an area that must be ready for commissioning, or a level that must be dried in before finishes start. Float on the project finish says nothing about any of them. A phase can lose three weeks while the final completion holds, and the first anyone hears of it is the turnover walk.
Track each phase milestone separately. Each one then gets its own driving path, its own float history and its own list of the activities that moved it.