AI delay analysis

AI Delay Analysis Grounded in Schedule Evidence

Pathizer measures delay and recovery on each phase milestone from your XER update history, then AI drafts the explanation over those measured figures.

AI delay analysis means using a language model to explain delay that was measured from the schedule. Pathizer measures it first. For each pair of updates, it calculates how far each phase milestone moved and which activities on the driving path moved it. The model drafts the explanation over those figures, and the draft is labelled for review.

Measured first: how a window's movement is classified

Each window runs from one data date to the next. Pathizer classifies the movement in it by what had happened by the window's data date. An activity that actually started or finished by then, or that the prior update planned to start or finish by then, carries actual movement. An activity that sat entirely in the future in both updates carries a Half-Step change. This is a revision of the forecast, charged to Half-Step Adjustments and not to a party.

A start that could not happen because its predecessor had not finished is treated as inherited, not as the activity's own failure. A later update can show a slipped activity actually finishing late. The slip it carried as a Half-Step is then reclassified as actual movement in the window where it first appeared. Each window then reconciles to the phase's total float variance.

Where each activity's contractor comes from

Attribution by contractor is only as good as the contractor on each activity. By default, Pathizer uses the schedule's resource assignments. It does this when the latest update has at least two distinct resources and three quarters of its work activities carry one. Failing that, it looks for an existing MasterFormat style activity code assigned to at least half the activities. When the file has neither, it generates a 16-division code from activity names and WBS. A language model proposes each activity's division, and fixed rules cover anything the model does not return. The uploaded XER is not edited.

You can pick a different activity code as the Contractor Source in the project's analysis settings, and an explicit choice is never overridden. Check the source before reading any contractor total.

Where General-Purpose AI Goes Wrong

Schedule answers need CPM logic and XER evidence.

  • Asked who caused a delay, a general-purpose model will name a party, even when the schedule does not support it.
  • Without the relationships and calendars it cannot tell if a late activity was on the driving path or had float to spare.
  • A summary that blends milestone delay, completion delay and contract entitlement reads as one finding when each is a separate question.

How Pathizer Handles It

The figures come from the parsed XER and the analysis run.

  • The days and the driving activities come from the analysis engine, not from the model.
  • Each window's figures trace back to the two XER exports that produced them.
  • Entitlement, responsibility and concurrency stay with the analyst and the contract.

Who It Is For

Explaining delay to a milestone without letting the model invent the cause

Forensic analystsClaims consultantsOwnersGeneral contractors

What Pathizer Does

Measure the movement of each phase milestone window by window, from one data date to the next.

Attribute that movement to the activities on the longest float path to the milestone, with each activity's contractor taken from the project's contractor source.

Split each window into progress movement and revision movement with Half-Step Adjustment Search.

Draft the delay narrative with AI over the measured figures, labelled for the analyst to review and edit.

Definitions

Terms used on this page.

Delay attribution

Tying the movement of a milestone in one update window to the activities on the path that drove it. In Pathizer it is read from the schedule record and kept separate from responsibility under the contract.

Recovery

Days a milestone gained back between two updates. Pathizer measures and attributes recovery the same way as delay and reports the two separately. It does not net them.

Practical Outputs

What you get.

Milestone movement per update window

Driving activities and contractors per window

Progress and revision movement split per window

A drafted delay narrative for review

Related Workflows

Related pages.

FAQ

Open your latest schedule update. Add last month's to see what changed. The free tools need no account.

Review my schedule update

Each finding traces back to the schedule export it came from.

When the update history cannot tie a day of movement to a party, Pathizer leaves that day unattributed. It does not split the day pro rata or round it into the largest share.