Window analysis vs. Time Impact Analysis
The phrase window analysis TIA is often used broadly in project controls, but the two methods are related, not identical. Window analysis is generally a retrospective or contemporaneous review of schedule movement across successive updates. Time Impact Analysis usually models a delay event in a current or accepted schedule update, often by inserting a fragnet to test its forecast impact.
A sound review states which method was used and how the windows were selected. It also states how the analysis treats actual progress, logic changes, mitigation, and concurrent delay events.
What a window analysis examines
Each window may be based on regular schedule update periods, major milestones or a change in the controlling path. It may also follow the start or completion of a delay event, or a material change in design, access, procurement, or site conditions.
Late activities are only the starting list. The analysis then determines if the delay affected the project's controlling path and if it moved a contractual milestone or completion date. A late design response may delay one activity yet have no effect on completion if float absorbs it. In another window, the same event may sit on a predecessor to a controlling milestone.
Information needed before starting
- Contract baseline and accepted revisions, with the schedule basis used for each period
- Native schedule files (XER), not only PDFs: logic, calendars, constraints, status, and float live in the native file
- Periodic schedule updates with data dates, actuals, remaining durations, and forecast dates
- Schedule narratives and change logs explaining why logic or durations changed
- Contemporaneous records: notices, RFIs, submittals, change directives, meeting minutes, daily reports
- Contract requirements: notice provisions, milestone definitions, approved analysis methods
Step 1: Define the objective and select windows
State what the review must answer: did a specific event affect the contractual completion date? Which activities controlled completion during a period? Was an alleged delay absorbed by float, offset by mitigation, or carried into a later window?
Choose windows that reflect the project's schedule history, not a preferred outcome. For each window, record the beginning and ending data dates, the schedule versions used and key milestones. Also record controlling and near-controlling paths, significant logic or calendar changes, and the delay events active during the period.
Step 2: Validate each schedule update
Before relying on an update, check that it is suitable for analysis. Check actual dates against project records, remaining durations and forecasts, open-ended activities, and constraints and imposed dates. Also check calendar assumptions, out-of-sequence progress, and unexplained logic or duration changes.
An update with weaknesses can still be analyzed, but the weaknesses should be disclosed and considered, not silently papered over. A clear limitation is more useful than a precise-looking result built on unsupported inputs.
Step 3: Identify the controlling path in each window
The critical path is the chain of work that controls the relevant completion milestone under the schedule's logic and status. It is not always the set of activities with the lowest float in a report. Note which activities drove the milestone and if the path changed from the last update. Note where float was consumed or created, and if progress or revised logic changed the result.
A delay to a non-controlling activity is not automatically a delay to completion. A delay can become critical later, once other work finishes or float is consumed.
Step 4: Map events to schedule activities and report
Connect each alleged delay event to specific schedule activities and relationships. Do not describe it only in narrative terms. Then report window by window: the schedule movement, the controlling path and the events active in the window. Report the support in contemporaneous records, and what the analysis cannot conclude.
How Pathizer supports window analysis
Pathizer reads XER updates (one active update per data date) and calculates the change from each update to the next. It finds added, deleted, and changed activities, finish-date movement and float-path changes. Half-Step Changes separate progress impacts from schedule revisions. Window Analysis (TIA) is live in Pathizer, and evidence views keep every finding traceable to the underlying schedule data. AI drafts narrative language for review. The analysis engine calculates every figure from the schedule data, not a model.