Read every float path to a phase milestone and see how its total float changed between updates, including the near-critical paths that can take over.

Float Path Intelligence is the name this page uses for reading float paths across updates. Pathizer does that work in two places. The Network Diagram draws the paths and the logic between them. The Continuous Float Attribution report tracks the activities on the longest float path to each phase milestone, window by window.

Why one critical path is not enough

Total float is how far an activity can slip before it moves the milestone it leads to. The critical path is the chain with the least of it. But a phase milestone usually has several chains behind it, separated by a few days of float. One bad update on the second or third chain can make it the driver. A review that only watches the critical path learns about it after the fact.

Float paths rank those chains: path 1 is the most critical, path 2 the next, and so on. Watching how each path's float moves from update to update shows which chain is eroding, not only which one is critical today.

How Pathizer evaluates and compares paths

For each phase milestone, Pathizer evaluates up to ten float paths by default from the XER's own relationships, calendars and data date. It keeps them for every update in the history. The Network Diagram draws them with the logic between their activities, colored by what moved them: impacts, recoveries, added activities and Half-Step adjustments.

Float in an XER is stored in hours on each activity's own calendar, so a five-day activity and a seven-day activity cannot be compared directly. Screens labelled Total Float CD convert it to calendar days on the calendar basis they state, and the file's own value is kept alongside.

Where General-Purpose AI Goes Wrong

Schedule answers need CPM logic and XER evidence.

  • A model cannot rank float paths without the relationship table, the calendars and the data date from the XER.
  • A summary of the critical path misses the near-critical path that becomes the driver two updates later.
  • Asked why a path lost float, a model without the update pair can only guess at which edit did it.

How Pathizer Handles It

The figures come from the parsed XER and the analysis run.

  • Paths are calculated from the XER's relationships and calendars before anything is explained.
  • Each update's driving path is kept, so a change of driver shows up in the update where it happened.
  • Ask Pathizer answers from the selected node's evidence and says so when that evidence is missing.

Who It Is For

For schedulers watching float run out on the path to a milestone

SchedulersProject controls leadsDelay analystsSuperintendents

What Pathizer Does

Draw phase paths and float paths with their relationships in the Network Diagram, so a driving path can be followed activity by activity.

Track total float on the longest float path to each phase milestone in every update window.

Show the update where a near-critical path took over as the driver, as a dated change on the Driver Gantt.

Ask Pathizer about a selected node and get an answer drawn from that node's evidence.

Definitions

Terms used on this page.

Float path

A chain of activities linked by relationships that leads to a milestone, ranked by total float. Scheduling software can calculate several. The first is the most critical. The next few are near-critical paths that may take over after a bad update.

Float erosion

Total float on an activity or path going down from one update to the next. Steady erosion on a near-critical path is often the first sign it will become the driver.

Practical Outputs

What you get.

Network Diagram of phase and float paths

Total float per path, per update

The update where the driver changed

Continuous Float Attribution report

Related Workflows

Related pages.

FAQ

Open your latest schedule update. Add last month's to see what changed. The free tools need no account.

Review my schedule update

Each finding traces back to the schedule export it came from.

When the update history cannot tie a day of movement to a party, Pathizer leaves that day unattributed. It does not split the day pro rata or round it into the largest share.