Why one critical path is not enough
Total float is how far an activity can slip before it moves the milestone it leads to. The critical path is the chain with the least of it. But a phase milestone usually has several chains behind it, separated by a few days of float. One bad update on the second or third chain can make it the driver. A review that only watches the critical path learns about it after the fact.
Float paths rank those chains: path 1 is the most critical, path 2 the next, and so on. Watching how each path's float moves from update to update shows which chain is eroding, not only which one is critical today.