Construction delay analysis: the methods, the records and how to choose

What a construction delay analysis measures, how the AACE 29R-03 methods differ and which records each one needs. How to run an analysis from schedule updates that a reviewer can retrace.

Angel Pans

By Angel Pans, Founder · October 8, 2026 · 10 min read

A late project raises three questions, and they are not the same question. Which events moved the completion date? By how many days? And under the contract, whose days are they? Delay analysis is the work of answering all three from the schedule record, in a way another scheduler can retrace.

This guide covers what a delay analysis measures and how the common methods differ. It also covers the records each method depends on and the mistakes that most often weaken a finished analysis.

What a delay analysis measures

A delay analysis connects an event to a change in the path that drives completion. An event that consumed float on a non-driving path may be real and well documented, and still have moved nothing. An event on the driving path may look small on paper and still set the finish date. The analysis has to show the path, not only the event.

It produces three things:

  • Cause: the event, the activities it touched and the record that shows when it happened.
  • Quantity: the days it added to the completion date or a contract milestone, measured against a named schedule.
  • Responsibility: which party carries the risk for those days under the contract, including periods where delays from more than one party overlap.

Delay and disruption are different claims. Delay moves a date. Disruption lowers productivity or forces a change in how work is done, sometimes without moving any date at all. Mixing the two in one analysis makes both harder to support.

Prospective and retrospective analysis

The first choice is timing.

A prospective analysis is done while the work is underway, usually when an event happens or a change is priced. It asks what the event is likely to do to the current schedule. Time Impact Analysis is the usual tool. Its value is that the time question gets settled close to the event, while the people and the records are still at hand.

A retrospective analysis is done after the fact, from the updates and records the project actually produced. It asks what did happen. Window analysis, as-planned versus as-built and collapsed as-built are retrospective methods.

Many disputes need both views: what the parties knew and forecast at the time, and what the as-built record later showed.

Where delay comes from, and what proves it

Most lists of causes look alike. They name weather, design changes, late approvals, long-lead procurement, labor and equipment availability, and schedules that were not realistic from the start. For the analysis, the cause matters less than the record behind it. For each category, ask which document fixes the date and the scope of the event.

Source of delayThe record that usually carries it
Weather and site conditionsDaily reports, weather data, the schedule's weather calendar
Design changes and late responsesRFI and submittal logs, change directives, revised drawings
Procurement and long-lead equipmentPurchase orders, submittal approvals, delivery records
Labor and equipment availabilityDaily reports, manpower logs, equipment records
Permits and inspectionsApplication and approval dates, inspection reports
Planning and logicThe baseline and each update's own logic, constraints and durations

The last row is different from the others. A schedule with open ends, hard constraints or unrealistic durations does not cause delay by itself, but it weakens every measurement taken from it. Checking the baseline and each update comes before any delay calculation, not after.

The methods, and what each one assumes

AACE International Recommended Practice 29R-03, Forensic Schedule Analysis, groups methods by how they treat the schedule. Observational methods read the updates as they were issued. Modeled methods add or subtract delays in a schedule model. The table lists the common methods with their 29R-03 protocol numbers.

MethodAACE 29R-03TimingWhat it needsWhat to watch
As-planned vs. as-builtMIP 3.1, 3.2RetrospectiveA baseline and actual datesShows that dates slipped, not reliably why
Window analysis (contemporaneous periods)MIP 3.3RetrospectiveEvery update as issuedNeeds a complete, consistent update history
Half-step (bifurcated) windowsMIP 3.4RetrospectiveEvery update as issuedSplits progress from revisions inside each window
Impacted as-plannedMIP 3.6EitherA baseline with sound logicIgnores actual progress and later logic changes
Time impact analysisMIP 3.7Usually prospectiveThe update current at each event, plus a fragnetEach fragnet needs its own evidence
Collapsed as-built (but-for)MIP 3.8RetrospectiveA reliable as-built scheduleDepends on how the as-built logic was rebuilt

Four of these carry most of the weight on a project with regular schedule updates.

Window analysis follows the schedule as it was actually updated. Each window runs from one data date to the next, and the analyst measures how the completion forecast and the driving path moved inside it. Because it uses the schedules the parties actually issued, it reflects what they knew at the time.

Half-step analysis splits each window in two. First, only the progress (actual dates and remaining durations) is applied to the earlier update. Then the logic, duration and scope revisions are applied. Movement in the first half came from how the work went; movement in the second came from changes to the plan. Without that split, a revision that recovered days can hide a progress slip of the same size. The window then reads as no change at all.

Time impact analysis inserts a fragnet representing the event into the update in effect when the event occurred, then recalculates. The change in the completion date is the modeled impact. It suits settling time while work continues, and it is only as good as the fragnet and the update it is placed in.

Collapsed as-built removes chosen delays from an as-built schedule to estimate when the project would have finished without them. It answers a but-for question, and it leans on how the as-built logic was reconstructed.

No method is correct in general. The choice follows the contract, the records that exist and the question being asked. A specification that prescribes a method settles the choice before anyone else does.

Running the analysis step by step

The method changes from project to project. The sequence of work stays much the same.

  1. Assemble the schedule record. Collect the approved baseline and every update after it, one schedule per data date. Where an update was revised and reissued, use the version that was actually submitted.
  2. Check each schedule. Open ends, constraints, out-of-sequence progress and duration changes limit what every later step can show. Record what you find. Do not fix it silently.
  3. Build the event list. For each candidate event, record the dates, the activities affected, the cause and the document that supports it.
  4. Measure. Apply the chosen method. Trace the longest path in each schedule, not only the activities flagged critical. Record the days each event or window moved the completion date or the milestone in question.
  5. Assign responsibility. Classify each delay under the contract: excusable or not, compensable or not. Where delays from different parties overlap on the driving path, mark the concurrent period explicitly.
  6. Report with the evidence attached. Each finding should point to the schedule rows and documents behind it. A reviewer can then retrace it without asking the analyst.

Concurrency, float and the contract

Two topics decide more disputes than the choice of method.

Concurrent delay is overlapping delay from different parties on the driving path in the same period. How concurrency affects time and money is set by the contract and the governing law, not by the schedule. The analysis should identify the overlapping periods clearly and leave the entitlement conclusion to that framework.

Float is shared by default under many contracts, but not all. A delay that consumes float without reaching the driving path may move no date. If the contract assigns float to one party, the same delay can carry different consequences. Read the float clause before measuring.

Alongside the contract, the Society of Construction Law Delay and Disruption Protocol is a widely used reference. It covers records, float, concurrency and assessing time while the work is still underway.

Mistakes that weaken a delay analysis

  • Choosing a method the record cannot support. A window analysis needs a complete update history. If updates are missing, say so and pick a method that fits.
  • Measuring against the wrong path. Activities flagged critical by a float threshold are not always the path driving completion. Trace the longest path.
  • Netting progress against revisions. A window that shows no movement may contain a slip and a recovery of equal size. A half-step split shows both.
  • Rebuilding the record late. Findings reconstructed months afterward from memory and partial records are harder to support than findings recorded update by update.
  • Missing notice requirements. A well measured delay can still fail on notice. Contract notice clauses run on their own clock.
  • Trusting a weak baseline. Every later measurement inherits the baseline's logic problems.

Where Pathizer fits

Pathizer reads your XER updates and keeps one active schedule per data date. The update history behind a window or half-step analysis lives in one place. Pathizer runs window analysis and Half-Step Changes across that history. It evaluates the float paths in each update and reports movement by phase and by contractor. Findings link back to the activities and relationships in your own XER files, so a reviewer can check the working, not only the result.

Pathizer implements the nine Method Implementation Protocols of AACE 29R-03. Its EOT ledger keeps granted days beside the measured delay and does not fold them in. The analysis is a tool for the scheduler or analyst. The conclusions, and any position on entitlement, stay with them.

See delay analysis, read the AACE MIP overview, or look up a term in the glossary.

Frequently asked questions

What is construction delay analysis? It identifies the events that moved a project's completion date or milestones. It measures the days each one caused against the project schedule and assigns responsibility for those days under the contract.

What is the difference between time impact analysis and window analysis? Time impact analysis models an event by inserting a fragnet into the update in effect when it happened, so it is usually prospective. Window analysis observes how the completion forecast and the driving path actually moved between consecutive updates, so it is retrospective.

What is a half-step analysis? It splits each update window into a progress step and a revision step. Movement caused by how the work went can then be separated from movement caused by changes to the plan.

Does every delayed activity delay the project? No. An activity delay moves completion only when it is on the driving path, or when it consumes enough float to reach it.

What records does a delay analysis need? The approved baseline, every update as submitted, daily reports, RFI and submittal logs, change orders, correspondence, meeting minutes and weather data.

Which method should I use? Start with the contract, which often names one. Otherwise choose by the question being asked and the records that exist. A complete update history supports window and half-step analysis, and a reliable as-built supports collapsed as-built.

Who performs delay analysis? Schedulers handle routine update to update analysis. Claims and disputes usually bring in a forensic scheduling consultant, sometimes serving as an expert witness.

Pathizer Project Controls Brief

Get the next project-controls guide

Practical guidance on schedule updates, project controls and clearer owner reports. Up to one guide a day. Confirm your email to subscribe.

Subscribe to Pathizer's blog newsletter. Unsubscribe in one click. This does not change your Pathizer account emails. Privacy policy.