Hospital and healthcare construction schedules

A hospital addition or renovation is usually built next to people who are sick, in a building that cannot close. How fast crews can work matters less to the schedule. What shapes it is when the facility can give up a corridor, a unit or a utility. It also depends on what has to be in place before anyone opens a ceiling. Those constraints are where a hospital schedule tends to move, and where the monthly narrative has to be careful.

A hospital wing under construction and a hand holding a schedule tablet

Phasing inside an occupied building

When a renovation runs in phases, each phase usually depends on the facility moving a department out of the space and back in again. Those moves belong in the schedule as milestones with the facility named as the party that controls them. If a department move slips, every phase behind it slips with it. The update should show that chain. It should not report it as slow progress by the trades.

Infection control and life safety before work starts

The CDC's guidelines for environmental infection control in health care facilities strongly support an infection control risk assessment. It comes before construction, renovation or other work that raises dust. The guidelines tie that assessment to the construction barriers the work needs. Accredited hospitals also put interim life safety measures in place when construction affects fire protection, exits or other life safety features.

For the schedule, those assessments and the barriers they call for are real work with real durations. If they are missing from the file, they come back later as inserted activities. Then the update shows a finish date that moved with no field progress to explain it. Building them in from the start keeps the logic honest, and makes it clear when a later change to precautions added time.

Shutdowns and tie-ins

Connecting new work to the existing building means planned shutdowns of power, medical gases, water or air handling. Each shutdown has to be agreed with the facility and is often limited to a set window. In the schedule, a shutdown works like a constrained milestone. If the window is missed, the next available one may be weeks away, and the activities behind it move as a block. Record the agreed date and who approved it next to each shutdown activity.

Owner-furnished medical equipment

When the owner buys imaging and other major equipment directly, its delivery sets the start for the rooms built around it. That delivery is a date the contractor does not control. Keep it as a dated milestone and write where the date came from. In each update, check how it changed: by a letter from the vendor, or by an edit in the file.

Inspection and approvals

Approvals are often a path of their own. In California, hospital projects under HCAI need an approved Inspector of Record before the building permit is issued. They also need a field approved testing, inspection and observation program before then. HCAI field staff monitor continuous inspection during construction. In any jurisdiction, inspections and approvals before occupancy belong in the schedule with the reviewing agency named. Then a review that runs long is visible as such.

What Pathizer does with a hospital schedule

Pathizer reads your XER updates and compares each one with the one before it. Update Review lists what changed between the latest and prior update. Added Activities / Fragnets lists every activity inserted between updates. So new precaution, shutdown or rework activities show up as insertions, and do not disappear into the baseline. The 6WLA Plan lists the next priority activities from the analyzed network. That helps when the next shutdown window is the date everyone is working to.

Executive schedule narratives draft an executive update memo from the latest schedule movement, for the scheduler to review before it goes to the owner. Report Generator prints phase and contractor reports without changing the analysis. The EOT Change Order / PCCO ledger keeps granted days and dollars per phase beside the schedule attribution.

Try it on your own files

Open your latest schedule update. Add last month's to see what changed. The free tools need no account. They are a screening, a first look before a full review.