Phasing inside an occupied building
When a renovation runs in phases, each phase usually depends on the facility moving a department out of the space and back in again. Those moves belong in the schedule as milestones with the facility named as the party that controls them. If a department move slips, every phase behind it slips with it. The update should show that chain. It should not report it as slow progress by the trades.