Work windows on an operating railroad
Federal roadway worker protection rules, 49 CFR Part 214 Subpart C, govern how work on or near track is protected. On controlled track, the working limits are set through exclusive track occupancy, foul time or train coordination. One roadway worker is in charge of each segment, and the dispatcher keeps a record of each authority. Contracts then define the windows themselves. Caltrain's contract language, for example, describes a work window as a designated period with a set start and end. In that period, track, signals and other operating elements are taken out of service for construction.
In the schedule file, a window is a calendar. Work that can only happen inside an outage should sit on a calendar that only has the granted hours. Then a cancelled or shortened window shows up as lost work periods, not as a vague slip. Record each granted window and the authority behind it next to the activities it serves. When a window is lost, the next one may be weeks away, and the update should show the block of work that moved with it.